PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING

Published on Slideshow
Static slideshow
Download PDF version
Download PDF version
Embed video
Share video
Ask about this video

Scene 1 (0s)

[Audio] Jeromiah Inc Proposed Two Storey Factory And Warehouse Building Project Update As Of August 09 2024 Good morning everyone. Project update as of August 9 2024..

Scene 2 (15s)

[Audio] Accomplishment As Of August 9 2024. 2. ACCOMPLISHMENT AS OF AUGUST 9, 2024.

Scene 3 (22s)

[Audio] Project Status Summary Project Timeline Date Original Contract Start: 6 November 2023 Original Contract Completion: 6 January 2025 Project Duration Date Contract Duration Days: 425 Days Days Elapsed: 270 Days Days To Go: 155 Days Overall Status To Date: (% Accomp.) (august 09) Projected Accomplishment %: 59.55% Actual Accomplishment %: 60.43% Variance : Plus 0.88% Days Delayed/ Advance: Plus 4 Days As of today 270 days have elapsed since the start of the project. We have 155 days remaining to complete the project. As of the latest update the project has achieved 60.43% of the planned milestones and objectives surpassing the projected accomplishment of 59.55%. This represents a positive advancement of 4 days ahead of the planned schedule..

Scene 4 (1m 41s)

4. [image].

Scene 5 (1m 47s)

[Audio] Civil / Structural Works Accomplishment photos for Structural Works.

Scene 6 (1m 54s)

[Audio] Accomplishment Report Stripping Of Form Enclosure At Second Floor Stair-1 Stiffener Columns Form Enclosure At Second Floor Stair-1 Lintel Beams.

Scene 7 (2m 8s)

[Audio] Field Density Test For Sog. Accomplishment Report.

Scene 8 (2m 18s)

[Audio] Installation Of Formworks For Second Floor Dust Collector Exterior Wall Installation Of Rebars For Vault Room.

Scene 9 (2m 28s)

[Audio] Soil Poisoning For Sog Phase 3. Accomplishment Report.

Scene 10 (2m 37s)

[Audio] Gravel Bedding At Sog Area 3 And Production Hallway Installation Of Rebar Mesh For Sog Area-2 Phase 2.

Scene 11 (2m 49s)

[Audio] Architectural Works. ARCHITECTURAL WORKS.

Scene 12 (2m 54s)

[Audio] Masonry Works. MASONRY WORKS. 12.

Scene 13 (3m 1s)

[Audio] Accomplishment Report Concrete Topping For Zocalo At Mixing Room 4 5 AND 6.

Scene 14 (3m 15s)

[Audio] Plastering Of Interior Wall At Staff Dorms.

Scene 15 (3m 27s)

[Audio] Formblocks Laying At Second Floor Elevator Walls Chb Laying At Stair-4 Wall Partition.

Scene 16 (3m 39s)

[Audio] Backfilling At Ground Floor Sog Phase 4 Concrete Pouring Of Stiffener Beam For Stair-1 Enclosure.

Scene 17 (3m 49s)

[Audio] Plastering At Front Exterior Wall Installation Of Groove Joints.

Scene 18 (4m 1s)

[Audio] Plastering At Front Exterior Wall Chb Laying At Second Floor Perimeter Wall.

Scene 19 (4m 13s)

[Audio] Formblocks Laying At Second Floor Elevator Area Zocalo For Warehouse Ramp And Stair.

Scene 20 (4m 26s)

[Audio] Clearing And Canting At Mezzanine Mixing Room 5 6 AND 7.

Scene 21 (4m 37s)

[Audio] Installation Of Formblocks For Second Floor Elevator Wall Concrete Pouring Of Zocalo For Warehouse Ramp.

Scene 22 (4m 49s)

[Audio] Plastering Of Wall For Stair-4 Enclosure Plastering Of Wall For Ground Floor Hallway.

Scene 23 (5m 0s)

[Audio] Mock-up For Goods Slide Chb Laying At Second Floor Rear Perimeter Along Gl: A-b/7.

Scene 24 (5m 11s)

[Audio] Plastering Of Wall Enclosure At Second Floor Stair-1 Form Enclosure For Lintel Beams At Elevator Walls.

Scene 25 (5m 24s)

[Audio] Installation Of Window Glass Frame At Mezzanine Mixing Room 4.

Scene 26 (5m 33s)

[Audio] Miscellaneous Steel Works. MISCELLANEOUS STEEL WORKS.

Scene 27 (5m 39s)

[Audio] Accomplishment Report Installation Of Rafters And Purlins.

Scene 28 (5m 51s)

[Audio] Installation Of Rafters For Roof Framing Roof Framing Status.

Scene 29 (6m 2s)

[Audio] Roof Framing Status As Of August 9 2024. Accomplishment Report.

Scene 30 (6m 12s)

[Audio] Installation Of Gi Pipes For Warehouse Ramp And Stair Railings.

Scene 31 (6m 22s)

[Audio] Installation Of Stainless Steel Railings At Stair-2 Installation Of Stainless Railings For Stair-2.

Scene 32 (6m 34s)

[Audio] Installation Of Stainless Steel Stair Railings At Stair-2.

Scene 33 (6m 44s)

[Audio] Painting Works. PAINTING WORKS. 33.

Scene 34 (6m 50s)

[Audio] Accomplishment Report Application Of Latex Paint At Storage High Ceiling Along Gl: F-g/7-5 Skim Coating At Second Floor Perimeter Wall Along Gl: F-g/7.

Scene 35 (7m 5s)

[Audio] Skim Coating At Ground Floor Warehouse Area Skim Coating Of Wall And Columns At Ground Floor Warehouse Area.

Scene 36 (7m 15s)

[Audio] Skim Coating At Ground Floor Warehouse Area Skim Coating At Ground Floor Warehouse Area.

Scene 37 (7m 24s)

[Audio] Skim Coating At Second Floor Warehouse Area Skim Coating Of Roof Beams.

Scene 38 (7m 33s)

[Audio] Application Of Primer Paint For Second Floor Underslab Skim Coating Of Walls And Ceiling At Ground Floor Area Along Gl: E-g/7-3.

Scene 39 (7m 48s)

[Audio] Skim Coating Of Wall And Beams At Ground Floor Warehouse Area Skim Coating Of Beams And Ceiling At Storage Area Along Gl: F-g/7-3.

Scene 40 (8m 3s)

40. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E- ESTEVES UAP CHITECT NUMBER OF DAYS Storage Area Material Recove" LÖiy. Ki*en Room Room Cold Stora# Rmm Room Pack" Azom 2 Nzom 3 Room 4 Packhg Naom 5 Packhg Room 6 R',om 7 Haeny at Area Washhg and Area Fernak Shc.er T Vale Changhg Room Y Shower and Toilet Secw$ Skep" kea STP control Room Room Pump Rcom and Storage Pres&fs Che and StorageEE Rcom Halway at Azea vaing Rcoms 01 02 Vaing Rcoms 03 Miing Vaing Rcoms 05 Vaing Rcoms 06 Rucoms 07 18 18.

Scene 41 (8m 23s)

41. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E. ESTEVES UAP CHITECT NUMBER OF DAYS.

Scene 42 (8m 54s)

[Audio] Waterproofing Works. WATERPROOFING WORKS.

Scene 43 (9m 0s)

[Audio] Accomplishment Report Application Of Waterproofing Membrane At Mixing Room 1.

Scene 44 (9m 9s)

[Audio] Jeromiah Procurement Status. JEROMIAH PROCUREMENT STATUS.

Scene 45 (9m 52s)

[Audio] Masonry And Plastering Schedule. MASONRY AND PLASTERING SCHEDULE.

Scene 46 (10m 15s)

[Audio] Safety Report Teach A Course. SAFETY REPORT.

Scene 47 (10m 22s)

[Audio] Mepfs Report. MEPFS REPORT. TEACH A COURSE.

Scene 48 (10m 28s)

[Audio] Weekly Construction Progress Report As Of August 09 2024 End Of Report Thank You! A Proposed 2-storey Factory And Warehouse Building.