PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING

1 of
Published on Video
Go to video
Download PDF version
Download PDF version
Embed video
Share video
Ask about this video

Page 1 (0s)

[Audio] Jeromiah Inc Proposed Two Storey Factory And Warehouse Building Project Update As Of August 09 2024 Good morning everyone. Project update as of August 9 2024..

Page 2 (15s)

[Audio] Accomplishment As Of August 9 2024. 2. ACCOMPLISHMENT AS OF AUGUST 9, 2024.

Page 3 (22s)

[Audio] Project Status Summary Project Timeline Date Original Contract Start: 6 November 2023 Original Contract Completion: 6 January 2025 Project Duration Date Contract Duration Days: 425 Days Days Elapsed: 270 Days Days To Go: 155 Days Overall Status To Date: (% Accomp.) (august 09) Projected Accomplishment %: 59.55% Actual Accomplishment %: 60.43% Variance : Plus 0.88% Days Delayed/ Advance: Plus 4 Days As of today 270 days have elapsed since the start of the project. We have 155 days remaining to complete the project. As of the latest update the project has achieved 60.43% of the planned milestones and objectives surpassing the projected accomplishment of 59.55%. This represents a positive advancement of 4 days ahead of the planned schedule..

Page 4 (1m 41s)

4. [image].

Page 5 (1m 47s)

[Audio] Civil / Structural Works Accomplishment photos for Structural Works.

Page 6 (1m 54s)

[Audio] Accomplishment Report Stripping Of Form Enclosure At Second Floor Stair-1 Stiffener Columns Form Enclosure At Second Floor Stair-1 Lintel Beams.

Page 7 (2m 8s)

[Audio] Field Density Test For Sog. Accomplishment Report.

Page 8 (2m 18s)

[Audio] Installation Of Formworks For Second Floor Dust Collector Exterior Wall Installation Of Rebars For Vault Room.

Page 9 (2m 28s)

[Audio] Soil Poisoning For Sog Phase 3. Accomplishment Report.

Page 10 (2m 37s)

[Audio] Gravel Bedding At Sog Area 3 And Production Hallway Installation Of Rebar Mesh For Sog Area-2 Phase 2.

Page 11 (2m 49s)

[Audio] Architectural Works. ARCHITECTURAL WORKS.

Page 12 (2m 54s)

[Audio] Masonry Works. MASONRY WORKS. 12.

Page 13 (3m 1s)

[Audio] Accomplishment Report Concrete Topping For Zocalo At Mixing Room 4 5 AND 6.

Page 14 (3m 15s)

[Audio] Plastering Of Interior Wall At Staff Dorms.

Page 15 (3m 27s)

[Audio] Formblocks Laying At Second Floor Elevator Walls Chb Laying At Stair-4 Wall Partition.

Page 16 (3m 39s)

[Audio] Backfilling At Ground Floor Sog Phase 4 Concrete Pouring Of Stiffener Beam For Stair-1 Enclosure.

Page 17 (3m 49s)

[Audio] Plastering At Front Exterior Wall Installation Of Groove Joints.

Page 18 (4m 1s)

[Audio] Plastering At Front Exterior Wall Chb Laying At Second Floor Perimeter Wall.

Page 19 (4m 13s)

[Audio] Formblocks Laying At Second Floor Elevator Area Zocalo For Warehouse Ramp And Stair.

Page 20 (4m 26s)

[Audio] Clearing And Canting At Mezzanine Mixing Room 5 6 AND 7.

Page 21 (4m 37s)

[Audio] Installation Of Formblocks For Second Floor Elevator Wall Concrete Pouring Of Zocalo For Warehouse Ramp.

Page 22 (4m 49s)

[Audio] Plastering Of Wall For Stair-4 Enclosure Plastering Of Wall For Ground Floor Hallway.

Page 23 (5m 0s)

[Audio] Mock-up For Goods Slide Chb Laying At Second Floor Rear Perimeter Along Gl: A-b/7.

Page 24 (5m 11s)

[Audio] Plastering Of Wall Enclosure At Second Floor Stair-1 Form Enclosure For Lintel Beams At Elevator Walls.

Page 25 (5m 24s)

[Audio] Installation Of Window Glass Frame At Mezzanine Mixing Room 4.

Page 26 (5m 33s)

[Audio] Miscellaneous Steel Works. MISCELLANEOUS STEEL WORKS.

Page 27 (5m 39s)

[Audio] Accomplishment Report Installation Of Rafters And Purlins.

Page 28 (5m 51s)

[Audio] Installation Of Rafters For Roof Framing Roof Framing Status.

Page 29 (6m 2s)

[Audio] Roof Framing Status As Of August 9 2024. Accomplishment Report.

Page 30 (6m 12s)

[Audio] Installation Of Gi Pipes For Warehouse Ramp And Stair Railings.

Page 31 (6m 22s)

[Audio] Installation Of Stainless Steel Railings At Stair-2 Installation Of Stainless Railings For Stair-2.

Page 32 (6m 34s)

[Audio] Installation Of Stainless Steel Stair Railings At Stair-2.

Page 33 (6m 44s)

[Audio] Painting Works. PAINTING WORKS. 33.

Page 34 (6m 50s)

[Audio] Accomplishment Report Application Of Latex Paint At Storage High Ceiling Along Gl: F-g/7-5 Skim Coating At Second Floor Perimeter Wall Along Gl: F-g/7.

Page 35 (7m 5s)

[Audio] Skim Coating At Ground Floor Warehouse Area Skim Coating Of Wall And Columns At Ground Floor Warehouse Area.

Page 36 (7m 15s)

[Audio] Skim Coating At Ground Floor Warehouse Area Skim Coating At Ground Floor Warehouse Area.

Page 37 (7m 24s)

[Audio] Skim Coating At Second Floor Warehouse Area Skim Coating Of Roof Beams.

Page 38 (7m 33s)

[Audio] Application Of Primer Paint For Second Floor Underslab Skim Coating Of Walls And Ceiling At Ground Floor Area Along Gl: E-g/7-3.

Page 39 (7m 48s)

[Audio] Skim Coating Of Wall And Beams At Ground Floor Warehouse Area Skim Coating Of Beams And Ceiling At Storage Area Along Gl: F-g/7-3.

Page 40 (8m 3s)

40. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E- ESTEVES UAP CHITECT NUMBER OF DAYS Storage Area Material Recove" LÖiy. Ki*en Room Room Cold Stora# Rmm Room Pack" Azom 2 Nzom 3 Room 4 Packhg Naom 5 Packhg Room 6 R',om 7 Haeny at Area Washhg and Area Fernak Shc.er T Vale Changhg Room Y Shower and Toilet Secw$ Skep" kea STP control Room Room Pump Rcom and Storage Pres&fs Che and StorageEE Rcom Halway at Azea vaing Rcoms 01 02 Vaing Rcoms 03 Miing Vaing Rcoms 05 Vaing Rcoms 06 Rucoms 07 18 18.

Page 41 (8m 23s)

41. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E. ESTEVES UAP CHITECT NUMBER OF DAYS.

Page 42 (8m 54s)

[Audio] Waterproofing Works. WATERPROOFING WORKS.

Page 43 (9m 0s)

[Audio] Accomplishment Report Application Of Waterproofing Membrane At Mixing Room 1.

Page 44 (9m 9s)

[Audio] Jeromiah Procurement Status. JEROMIAH PROCUREMENT STATUS.

Page 45 (9m 52s)

[Audio] Masonry And Plastering Schedule. MASONRY AND PLASTERING SCHEDULE.

Page 46 (10m 15s)

[Audio] Safety Report Teach A Course. SAFETY REPORT.

Page 47 (10m 22s)

[Audio] Mepfs Report. MEPFS REPORT. TEACH A COURSE.

Page 48 (10m 28s)

[Audio] Weekly Construction Progress Report As Of August 09 2024 End Of Report Thank You! A Proposed 2-storey Factory And Warehouse Building.