Page 1 (0s)

[Audio] Good morning everyone. Project update as of August 9 2024..

Page 2 (9s)

[Audio] Breakdown and Remaining Percentage of our project..

Page 3 (21s)

[Audio] Based on the accomplishment our project is ahead by 4 days..

Page 4 (40s)

[Audio] As of today 270 days have elapsed since the start of the project. We have 155 days remaining to complete the project. As of the latest update the project has achieved 60.43% of the planned milestones and objectives surpassing the projected accomplishment of 59.55%. This represents a positive advancement of 4 days ahead of the planned schedule..

Page 5 (1m 8s)

5. [image].

Page 6 (1m 14s)

[Audio] Accomplishment photos for Structural Works.

Page 7 (1m 20s)

[Audio] Stripping Of Form Enclosure At Second Floor Stair-1 Stiffener Columns. Form Enclosure At Second Floor Stair-1 Lintel Beams..

Page 8 (1m 35s)

[Audio] Field Density Test For S O G. Accomplishment Report.

Page 9 (1m 44s)

[Audio] Installation Of Formworks For Second Floor Dust Collector Exterior Wall. Installation Of Rebars For Vault Room..

Page 10 (1m 55s)

[Audio] Soil Poisoning For S O G Phase 3.. Accomplishment Report.

Page 11 (2m 3s)

[Audio] Gravel Bedding At S O G Area 3 And Production Hallway. Installation Of Rebar Mesh For S O G Area-2 Phase 2..

Page 12 (2m 15s)

[Audio] Accomplishment Report For Architectural Works..

Page 13 (2m 21s)

[Audio] Masonry Works.. MASONRY WORKS. 13.

Page 14 (2m 27s)

[Audio] Concrete Topping For Zocalo At Mixing Room 4 5 AND 6..

Page 15 (2m 42s)

[Audio] Plastering Of Interior Wall At Staff Dorms..

Page 16 (2m 54s)

[Audio] Formblocks Laying At Second Floor Elevator Walls. Chb Laying At Stair-4 Wall Partition..

Page 17 (3m 6s)

[Audio] Concrete Pouring Of Stiffener Beam For Stair-1 Enclosure. Backfilling At Ground Floor S O G Phase 4..

Page 18 (3m 16s)

[Audio] Plastering At Front Exterior Wall. Installation Of Groove Joints..

Page 19 (3m 27s)

[Audio] Plastering At Front Exterior Wall. Chb Laying At Second Floor Perimeter Wall..

Page 20 (3m 39s)

[Audio] Formblocks Laying At Second Floor Elevator Area. Zocalo For Warehouse Ramp And Stair..

Page 21 (3m 52s)

[Audio] Clearing And Canting At Mezzanine Mixing Room 5 6 AND 7. Zocalo For Warehouse Ramp And Stair..

Page 22 (4m 3s)

[Audio] Installation Of Formblocks For Second Floor Elevator Wall. Concrete Pouring Of Zocalo For Warehouse Ramp..

Page 23 (4m 16s)

[Audio] Plastering Of Wall For Stair-4 Enclosure. Plastering Of Wall For Ground Floor Hallway..

Page 24 (4m 27s)

[Audio] Mock-up For Goods Slide. Chb Laying At Second Floor Rear Perimeter Along Gl: A-b/7.

Page 25 (4m 38s)

[Audio] Plastering Of Wall Enclosure At Second Floor Stair-1. Form Enclosure For Lintel Beams At Elevator Walls..

Page 26 (4m 50s)

[Audio] Left Side View. Rear Side View.. Accomplishment Report.

Page 27 (4m 59s)

[Audio] Right Side View. Front View.. Accomplishment Report.

Page 28 (5m 7s)

[Audio] Aluminum Doors And Windows.. ALUMINUM DOORS AND WINDOWS.

Page 29 (5m 14s)

[Audio] Installation Of Window Glass Frame At Mezzanine Mixing Room 4..

Page 30 (5m 24s)

[Audio] Miscellaneous Steel Works. MISCELLANEOUS STEEL WORKS.

Page 31 (5m 31s)

[Audio] Installation Of Rafters And Purlins.. Accomplishment Report.

Page 32 (5m 42s)

[Audio] Installation Of Rafters For Roof Framing..

Page 33 (5m 53s)

[Audio] Roof Framing Status As Of August 9 2024..

Page 34 (6m 3s)

[Audio] Installation Of G I Pipes For Warehouse Ramp And Stair Railings..

Page 35 (6m 12s)

[Audio] Installation Of Stainless Steel Railings At Stair-2..

Page 36 (6m 23s)

[Audio] Painting Works.. PAINTING WORKS. 36.

Page 37 (6m 29s)

[Audio] Application Of Latex Paint At Storage High Ceiling Along Gl: F-g/7-5. Skim Coating At Second Floor Perimeter Wall Along Gl: F-g/7..

Page 38 (6m 44s)

[Audio] Skim Coating At Ground Floor Warehouse Area. Skim Coating Of Wall And Columns At Ground Floor Warehouse Area..

Page 39 (6m 55s)

[Audio] Skim Coating At Ground Floor Warehouse Area. Painting At Ramp Railings At Ground Floor..

Page 40 (7m 4s)

[Audio] Skim Coating At Second Floor Warehouse Area. Skim Coating Of Roof Beams..

Page 41 (7m 13s)

[Audio] Application Of Primer Paint For Second Floor Underslab. Skim Coating Of Walls And Ceiling At Ground Floor Area Along Gl: E-g/7-3..

Page 42 (7m 28s)

[Audio] Skim Coating Of Wall And Beams At Ground Floor Warehouse Area. Skim Coating Of Beams And Ceiling At Storage Area Along Gl: F-g/7-3..

Page 43 (7m 43s)

[Audio] Painting Works Schedule. 43. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E- ESTEVES UAP CHITECT NUMBER OF DAYS Storage Area Material Recove" LÖiy. Ki*en Room Room Cold Stora# Rmm Room Pack" Azom 2 Nzom 3 Room 4 Packhg Naom 5 Packhg Room 6 R',om 7 Haeny at Area Washhg and Area Fernak Shc.er T Vale Changhg Room Y Shower and Toilet Secw$ Skep" kea STP control Room Room Pump Rcom and Storage Pres&fs Che and StorageEE Rcom Halway at Azea vaing Rcoms 01 02 Vaing Rcoms 03 Miing Vaing Rcoms 05 Vaing Rcoms 06 Rucoms 07 18 18.

Page 44 (8m 3s)

[Audio] Painting Works Schedule. 44. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E. ESTEVES UAP CHITECT NUMBER OF DAYS.

Page 45 (8m 34s)

[Audio] Waterproofing Works.. WATERPROOFING WORKS.

Page 46 (8m 40s)

[Audio] Application Of Waterproofing Membrane At Mixing Room 1..

Page 47 (8m 49s)

[Audio] Jeromiah Procurement Status As Of August 9 2024..

Page 48 (9m 31s)

[Audio] Masonry And Plastering Schedule For The Month Of August.