PROJECT UPDATE AS OF AUGUST 09, 2024. PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING.

Page 2 (9s)

2. [image] TEM DESCRIPTION TOTAL AMOUNT FOR CIVIL WORKS UNIT QTY 46.33% TOTAL AMOUN so. 805.756.15 38.11% PREVIOUS VALUE 7469428347 CURRENT VALUE 1.82% "69,080.86 39.80% TO DATE VALUE Remaining parcanta.

Page 3 (21s)

3. [image] TEM DESCRIPTION NO. TOTAL AMOUNT FOR FINISHING WORKS 100.00% UNIT QTY WT.% 24.95% 28.73% TOTAL AMOUNT 196.000.ooo.oo PREVIOUS VALUE WT.% WT.% 9.13% 9.26% 59.19% CURRENT VALUE WT.% 10.18% 9.72% 60.43% TO DATE VALUE TOTAL AMOUNT FOR MEPF WORKS GRAND TOTAL 17,893,755.29 109.975.201.97 1.05% 0.85% 0.57% Remaining Percentage 39.57% 39.57%.

Page 4 (40s)

4. PROJECT TIMELINE DATE ORIGINAL CONTRACT START: 6 NOVEMBER 2023 ORIGINAL CONTRACT COMPLETION: 6 JANUARY 2025.

Page 5 (1m 1s)

5. [image].

Page 6 (1m 7s)

CIVIL / STRUCTURAL WORKS. 6.

Page 7 (1m 14s)

Accomplishment Report. STRIPPING OF FORM ENCLOSURE AT SECOND FLOOR STAIR-1 STIFFENER COLUMNS.

Page 8 (1m 28s)

Accomplishment Report. FIELD DENSITY TEST FOR SOG.

Page 9 (1m 37s)

Accomplishment Report. INSTALLATION OF FORMWORKS FOR SECOND FLOOR DUST COLLECTOR EXTERIOR WALL.

Page 10 (1m 48s)

Accomplishment Report. SOIL POISONING FOR SOG PHASE 3.

Page 11 (1m 56s)

Accomplishment Report. GRAVEL BEDDING AT SOG AREA 3 AND PRODUCTION HALLWAY.

Page 12 (2m 8s)

ARCHITECTURAL WORKS. 12.

Page 13 (2m 14s)

MASONRY WORKS. 13.

Page 14 (2m 20s)

Accomplishment Report. CONCRETE TOPPING FOR ZOCALO AT MIXING ROOM 4, 5, AND 6.

Page 15 (2m 35s)

Accomplishment Report. PLASTERING OF INTERIOR WALL AT STAFF DORMS.

Page 16 (2m 47s)

Accomplishment Report. FORMBLOCKS LAYING AT SECOND FLOOR ELEVATOR WALLS.

Page 17 (2m 59s)

Accomplishment Report. CONCRETE POURING OF STIFFENER BEAM FOR STAIR-1 ENCLOSURE.

Page 18 (3m 9s)

Accomplishment Report. PLASTERING AT FRONT EXTERIOR WALL.

Page 19 (3m 20s)

Accomplishment Report. PLASTERING AT FRONT EXTERIOR WALL.

Page 20 (3m 33s)

Accomplishment Report. FORMBLOCKS LAYING AT SECOND FLOOR ELEVATOR AREA.

Page 21 (3m 46s)

Accomplishment Report. CLEARING AND CANTING AT MEZZANINE MIXING ROOM 5, 6, AND 7.

Page 22 (3m 57s)

Accomplishment Report. INSTALLATION OF FORMBLOCKS FOR SECOND FLOOR ELEVATOR WALL.

Page 23 (4m 9s)

Accomplishment Report. PLASTERING OF WALL FOR STAIR-4 ENCLOSURE.

Page 24 (4m 20s)

Accomplishment Report. MOCK-UP FOR GOODS SLIDE. 24.

Page 25 (4m 31s)

Accomplishment Report. PLASTERING OF WALL ENCLOSURE AT SECOND FLOOR STAIR-1.

Page 26 (4m 44s)

Accomplishment Report. LEFT SIDE VIEW. 26. REAR SIDE VIEW.

Page 27 (4m 52s)

Accomplishment Report. RIGHT SIDE VIEW. 27. FRONT VIEW.

Page 28 (5m 1s)

ALUMINUM DOORS AND WINDOWS. 28.

Page 29 (5m 7s)

Accomplishment Report. INSTALLATION OF WINDOW GLASS FRAME AT MEZZANINE MIXING ROOM 4.

Page 30 (5m 18s)

MISCELLANEOUS STEEL WORKS. 30.

Page 31 (5m 24s)

Accomplishment Report. INSTALLATION OF RAFTERS AND PURLINS.

Page 32 (5m 35s)

Accomplishment Report. INSTALLATION OF RAFTERS FOR ROOF FRAMING.

Page 33 (5m 47s)

Accomplishment Report. ROOF FRAMING STATUS AS OF AUGUST 9, 2024.

Page 34 (5m 56s)

Accomplishment Report. INSTALLATION OF GI PIPES FOR WAREHOUSE RAMP AND STAIR RAILINGS.

Page 35 (6m 6s)

Accomplishment Report. INSTALLATION OF STAINLESS STEEL RAILINGS AT STAIR-2.

Page 36 (6m 17s)

PAINTING WORKS. 36.

Page 37 (6m 23s)

Accomplishment Report. APPLICATION OF LATEX PAINT AT STORAGE HIGH CEILING ALONG GL: F-G/7-5.

Page 38 (6m 38s)

Accomplishment Report. SKIM COATING AT GROUND FLOOR WAREHOUSE AREA.

Page 39 (6m 49s)

Accomplishment Report. SKIM COATING AT GROUND FLOOR WAREHOUSE AREA.

Page 40 (6m 58s)

Accomplishment Report. SKIM COATING AT SECOND FLOOR WAREHOUSE AREA.

Page 41 (7m 7s)

Accomplishment Report. APPLICATION OF PRIMER PAINT FOR SECOND FLOOR UNDERSLAB.

Page 42 (7m 21s)

Accomplishment Report. SKIM COATING OF WALL AND BEAMS AT GROUND FLOOR WAREHOUSE AREA.

Page 43 (7m 36s)

43. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E- ESTEVES UAP CHITECT NUMBER OF DAYS Storage Area Material Recove" LÖiy. Ki*en Room Room Cold Stora# Rmm Room Pack" Azom 2 Nzom 3 Room 4 Packhg Naom 5 Packhg Room 6 R',om 7 Haeny at Area Washhg and Area Fernak Shc.er T Vale Changhg Room Y Shower and Toilet Secw$ Skep" kea STP control Room Room Pump Rcom and Storage Pres&fs Che and StorageEE Rcom Halway at Azea vaing Rcoms 01 02 Vaing Rcoms 03 Miing Vaing Rcoms 05 Vaing Rcoms 06 Rucoms 07 18 18.

Page 44 (7m 56s)

44. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E. ESTEVES UAP CHITECT NUMBER OF DAYS.

Page 45 (8m 27s)

WATERPROOFING WORKS. 45.

Page 46 (8m 34s)

Accomplishment Report. APPLICATION OF WATERPROOFING MEMBRANE AT MIXING ROOM 1.

Page 47 (8m 42s)

JEROMIAH PROCUREMENT STATUS. 47. [image] ITEM NO. 14 15 DESCRIPT ION STAINLESSWATERTANK TRADECON FOR PRECAST WALL WATERPROOFING FLOOR FINISH (HARDENER) PUMPS PANTING WORKS SILKAL FLOOR FINISH CEILING WORKS ALUMINUM DOORS WINDOWS METAL DOORS STEEL WORKS FINISHING HARDWARES (LOCKSET) EIFSFORWINDOW ALUMINUM CLADDING PANEL COUNTER TOP TOILET PARTITION DATESU8MffTEDTO IMA MARCH 04, 2024 MARCH 04, 2024 APRIL 12, 2024 MARCH 25, 2024 MARCH 21 2024 MAY03, 2024 MAY 27, 2024 JUNE 03, 2024 APRIL 2024 MAY02, 2024 MAY21 2024 MAY MAY21, 2024 DATE APPROVED ay MARCH 06, 2024 MARCH 26, 2024 APRIL 16, 2024 11 , 2024 APRIL 16, 2024 MAY 2024 JULY 30, 2024 JUNE 05, 2024 MAY 02, 2024 MAY 21, 2024 MAY 21, 2024 MAY 23, 2024 MAY 21, 2024 DATEOF MR MARCH 08, 2024 MARCH 26, 2024 APRIL 16, 2024 APRIL 11 , 2024 APRIL 16, 2024 MAY08, 2024 JULY 30, 2024 JUNE05,2024 MAY 03, 2024 MAY 21, 2024 JUNE 06, 2024 MAY 24, 2024 MAY 21, 2024 DATE APPROVED ay MARCH 11, 2024 MARCH 26, 2024 APRIL 16, 2024 APRIL 11 , 2024 APRIL 16, 2024 MAY 15, 2024 JUNE05,2024 JUNE 07,2024 MAY 30, 2024 JUNE21 , 2024 JULY 25, 2024 MAY 28, 2024 REMARKSST AT US CHUAN HING ESICOR VAZTECH COLOURTECH WAITING FORAPPROVAL OF MR MARCON WIL-AN ALUMINUM MET ROT ECH BASTIEN MET ROT ECH GS GO BROS.

Page 48 (9m 25s)

MASONRY AND PLASTERING SCHEDULE. 48. [image] Work Item 1.0 Ground Floor Stair-4 and Rea- Wall GLA to D Perimeter Fence at Front GL I-H (Pandingdueto Meralco) Perimeter Fence at Front GL I/ 3-D (Pending Duet" Gate) Demo K itchen Vault Rcom Stair-5 2.0 Mezzanine Floor Laundry Area Staff Dorm I and 2 Toilet Office To i Ets Stair-4 and Rea- Wall GLA to D Ekvator Form bOck 3.0 2nd Floor Dust Coletor (D-F) Stair-I Ekvator Form bOck Stair-4 and Rea- Wall GLA to D 4.0 Roomeck Parapa @Right Parapa @Reå Parapa @Front 5.0 Exterior Front Right Let (Retouching of Pr aast) Rear.

Page 49 (9m 48s)

SAFETY REPORT. TEACH A COURSE. 49.

Page 50 (9m 55s)

SAFETY MANPOWER REPORT.