Scene 1 (0s)

[Audio] Video Sop For Complete Power Failure At Cch.

Scene 2 (4s)

[Audio] STEP-0 The operator must not panic & keep calm to avoid any mishap regarding his own safety. Operator must be in all mandatory PPEs Securing seal air is the first top-most priority in this case. The operator must immediately reach the seal air tank using portable torch lights available at site & close the inlet & outlet valves of the seal air tank in order to secure seal air available in the tank. Close the seal air valve from header. Seal air-line valve to all compressors should be closed. Shift control must be informed immediately of the situation & the nature of interruption. Shift control is in real time communication with the concerned electrical team..

Scene 3 (19s)

[Audio] STEP-1 Close the Seal Air receiver Inlet Line valve immediately (V -1).

Scene 4 (29s)

[Audio] STEP-2 Check the Seal Air Receiver Tank outlet valve in close position (V -2).

Scene 5 (39s)

[Audio] STEP-3 Close the Header Seal Airline valve immediately (V -3).

Scene 6 (49s)

[Audio] STEP-4 Check the Seal Air Interconnection line valve is in close position (V -4).

Scene 7 (59s)

[Audio] STEP-5 Close the Inlet Seal Air Valve of all the Compressors individually.

Scene 8 (1m 9s)

[Audio] STEP-6 Close the Service Air Receiver Tank inlet valve immediately (V-6).

Scene 9 (1m 19s)

[Audio] STEP-7 Shift In-Charge will contact Electrical Shift In-charge, once Power is up for the revival of the system. Concerned electrical team gives clearance for starting equipment..

Scene 10 (1m 29s)

[Audio] STEP-8 Start Cooling Tower Fan as per the instruction of Electrical & Operation Shift In-charge.

Scene 11 (1m 39s)

[Audio] STEP-9 Start Cooling Water Pump as per instruction of Electrical & Operation Shift In-charge.

Scene 12 (1m 49s)

[Audio] STEP-10 Open the Seal Air Interconnection line valve (V-4).

Scene 13 (1m 59s)

[Audio] STEP-11 Open the Screw Compressor discharge Valve (V-4).

Scene 14 (2m 8s)

[Audio] STEP-12 Start the Seal Air Comp. as per instruction of Electrical & Operation Shift In-charge.

Scene 15 (2m 18s)

[Audio] STEP-13 Open the Seal Air Receiver Tank outlet valve (V-2).

Scene 16 (2m 28s)

[Audio] STEP-14 Open seal airline & start Comp. individually after checking all parameters..

Scene 17 (2m 38s)

[Audio] STEP-15 Start Air Dryers as per instruction of Electrical & Operation Shift In-charge.

Scene 18 (2m 48s)

[Audio] STEP-16 Continuous monitoring the Instrument & Mist Air Pressure Gauge.

Scene 19 (2m 58s)

[Audio] STEP-17 Partially open Seal air receiver Inlet Line valve Pressure reach at 6 KG/CM­² (V -1).

Scene 20 (3m 8s)

[Audio] STEP-18 Gradually open the Service Air Receiver inlet valve after air pressure reaches at 6.5 KG/CM² (V -5).

Scene 21 (3m 18s)

[Audio] STEP-19 Open the Header Seal Airline and normalize the operation (V 3).

Scene 22 (3m 28s)

[Audio] STEP-20 After normalize the operation discuss with team & carry forward to team leader.