[Audio] Thank you for inviting us today. On behalf of United Engineering Construction (UNEC), it is our pleasure to present our proposal to Nakheel for the Palm Jebel Ali Fronds K & L. We are excited about the opportunity to collaborate with Nakheel, a leader in real estate. Our presentation will highlight our commitment to quality, and innovation, demonstrating how UNEC's expertise aligns with Nakheel's vision for this project..
[Audio] Table of Content Project logistics & Mobilization Engineering procedure Procurement procedure Execution Team Execution proposal Equipment Program Resource Management.
[Audio] Project Logistics and mobilization. PROJECT LOGISTICS & MOBILIZATION.
[Audio] The project is located in Palm Jebel Ali, specifically on Fronds K & L. This artificial archipelago was relaunched in 2023. Palm Jebel Ali is 50% larger than Palm Jumeirah and comprises 16 fronds..
[Audio] This map shows the access route from Sheikh Zayed Road to thew site on Fronds K & L..
[Audio] The highlighted area indicates the locations of the employer, PMC, Engineer, and UNEC management offices..
[Audio] These layouts depict the proposed office arrangements as per the employer's requirements outlined in the tender documents..
[Audio] Certain areas within the premium villa lands will be designated for the site supervision team offices and labor facilities. This strategic allocation ensures that our team has the necessary resources and proximity to effectively manage and oversee the project's development..
[Audio] As outlined in the site logistics plan, the highlighted areas indicate the proposed locations designated for labor facilities and offices for the site supervision team. These areas have been specifically chosen to optimize operational efficiency and facilitate effective management oversight..
[Audio] The highlighted area indicates the location designated for the main store and laydown material..
[Audio] Certain lands inside the fronds will be temporarily utilized for the storage of laydown material..
[Audio] Project Engineering Procedure. 1,200+ Woman Engineer On Site Stock Illustrations, Royalty-Free Vector Graphics & Clip Art - iStock.
[Audio] Once the contract is awarded and upon receipt of IFC (Issued For Construction) documents, UNEC will commence all engineering activities. Each department will begin reviewing the documents and undertake the following tasks: The contract team will develop project protocols, insurance and guarantee bonds, and identify authorized signatories. The engineering team will establish submittal logs, prepare shop drawings, issue RFIs (Requests for Information), manage post-contract variations, NOCs (Notices of Completion), and mobilization plans. Concurrently, the commercial team will assist in developing cost codes, creating an execution budget, and defining work breakdown packages based on the baseline program. This structured approach ensures comprehensive preparation and coordination across all project phases..
[Audio] UNEC's in-house BIM team will develop coordinated models for the project's assets, utilizing data provided by engineers, specialists, and subcontractors. These models will undergo thorough clash detection to identify any conflicts. RFIs will then be raised to the engineer to seek further clarification and instructions for resolving these clashes. Once all clashes are successfully resolved and the final coordinated model is ready, UNEC will proceed to extract shop drawings. These drawings will be submitted to the engineer for comprehensive review and approval, ensuring alignment with project specifications and requirements..
[Audio] Project Procurement Procedure. 15. PROJECT PROCUREMENT PROCEDURE.
[Audio] The UNEC engineering and commercial teams will collaborate to prepare a list of suppliers and subcontractors, which will be submitted for engineer approval. Simultaneously, UNEC will send out Requests for Quotations along with related documents such as drawings, specifications, design reports, quantities, and draft warranties. Upon receiving quotations, the UNEC team will conduct a thorough analysis and select the winning bidder for each package, which will then be submitted for engineer approval. Once approved, UNEC will proceed to award the package to the selected bidders. Following the award, material and sample submittals will be prepared and submitted to the engineer for review and approval. This meticulous process ensures that all materials and subcontractors meet the project's standards and specifications..
[Audio] UNEC undertakes a pivotal role in the procurement process by presenting the proposed list of tenderers for each PS package to the engineer for approval. This includes issuing comprehensive tender documents to PS tenderers and specialists. Throughout this phase, UNEC ensures all inquiries and site visit requests from tenderers are coordinated and shared with the engineer to maintain transparency and alignment with project requirements. Upon receipt of quotations from tenderers, UNEC conducts thorough technical and commercial assessments. These assessments are compiled into a draft recommendation and assessment report, which are then submitted to both the engineer and employer for approval. Once endorsed by the employer, the engineer authorizes UNEC to proceed with signing the PS packages, whether in full or in part, with the selected tenderer. Following approval, UNEC proceeds to finalize contracts with the chosen tenderers, ensuring all contractual agreements are meticulously reviewed and executed to facilitate the seamless initiation of project activities. This methodical approach guarantees that procurement operations are conducted efficiently and in accordance with project timelines and specifications..
[Audio] I donno, check with dr latif. 18. MEP CONTRACTOR INFRASTRUCTURE CONTRACTOR PAINTING WORKS BLOCK WORKS CONCRETE SUPPLIER WATER PROOFING.
[Audio] Execution Team. 19. EXECUTION TEAM. Phases of the Construction Project - IIST.
[Audio] This chart provides an overview of the required engineering and supervision team specifically designated for Frond K..
[Audio] Similarly, this chart illustrates the necessary engineering and supervision team for Frond L..
[Audio] These individuals represent the proposed key personnel who are slated to lead the engineering team on-site..
[Audio] Execution Proposal. Construction Clipart Cartoon Construction Site Construction Site Vector Illustration, Cartoon Clipart, Construction Clipart, Construction PNG and Vector with Transparent Background for Free Download.
[Audio] Each frond is segmented into three primary zones, and each of these zones is subsequently divided into two smaller sub-zones. This provides a structured framework for effective planning and management of our project. This approach ensures clarity in operational processes and facilitates streamlined execution..
[Audio] In conclusion, today's presentation has provided a comprehensive overview of our project, initiative and goals. We are optimistic about our path forward, guided by a strategic approach and supported by our committed team.
[Audio] Thank you for your valuable time and engagement. We invite any questions or feedback you may have as we continue to progress towards our objectives..