PowerPoint Presentation

Published on Slideshow
Static slideshow
Download PDF version
Download PDF version
Embed video
Share video
Ask about this video

Scene 1 (0s)

CHAPTER 1:. CONCRETE. SIMPLIFIED CONSTRUCTION ESTIMATES BY MAX FAJARDO.

Scene 2 (11s)

1-1 PLAIN AND REINFORCED CONCRETE. Concrete is either plain or reinforced..

Scene 3 (40s)

AGGREGATES. Classification of Aggregates:. Course Aggregate such as crushed sone, crushed gravel or natural gravel with particles retained on a 5 mm sieve. Fine Aggregate such as crushed stone, crushed gravel, sand or natural sand with particles passing on a 5 mm sieve..

Scene 4 (55s)

1-2 THE PRINCIPLES OF CONCRETE MIXING. Requirements to meet in production of concrete mixture:.

Scene 5 (1m 12s)

Classification of Concrete Mixture: 1. Designed Mixture The contractor is responsible in establishing the mixture proportion that will achieve the required strength and workability as specified in the plan. 2. Prescribed Mixture The designing engineer specified the mixture proportion 1-3 THE UNIT OF MEASURE Prior to System International (SI), materials for concrete structures were estimated in terms of cubic meter although, the components thereof like; cement, sand, gravel, and water, are measured in pounds, cubic foot, and gallons per bag respectively..

Scene 6 (1m 37s)

TABLE 1-1 CONVERSION FROM INCHES TO METER. TABLE 1-1 CONVERSION FROM INCHES TO METER .Awtodn*e Ninet 10 11 12 13 14 15 16 17 18 20 .0254 .050B .0762 .1016 .1270 .1524 .1778 .2032 .228E .2540 .2794 3048 .3302 3556 3810 .4064 .431B 4572 .4826 .5080 02S 050 075 .100 .125 .150 .175 .200 225 .250 .275 .300 .325 .350 .375 400 .425 475 23 24 27 28 29 30 32 33 37 40 Acurü .5334 .5588 .5842 6350 .6858 .7112 .7620 .7874 .8128 8382 8636 .8890 .9144 .9398 9652 1.016 .525 .550 .575 .600 .625 .650 .675 .700 725 .750 77S .82S 875 .92S .975 1.00.

Scene 7 (2m 8s)

1-4 CONCRETE PROPORTION Two different ways in proportioning concrete mixture: By Weight By Volume Method.

Scene 8 (2m 36s)

In actual and masonry work, there are several factors that might affect the accuracy of the estimate. Some of which are enumerated as follows: Ordering of Course Aggregate must be Specific as to:.

Scene 9 (2m 49s)

1-5 CONCRETE SLAB. . to cm. FIGURE 1-2 CONCRETE PAVEMENT.

Scene 10 (2m 58s)

SOLUTION: 1. Determine the volume of the proposed concrete pavement. Volume = Thickness x Width x Length V = .10 x 3.00 x 5.00 V = 1.5 cubic meters 2. Refer to Table 1-2. Using 40 kg. cement class C mixture; multiply the volume by the corresponding values..

Scene 11 (3m 51s)

1-6 ESTIMATING CONCRETE SLAB BY THE AREA METHOD. TABLE 1-3 QUANTITY OF CEMENT, SAND AND GRAVEL FOR SLAB AND WALLS PER SQUARE METER AREA Mixture Class • Slab 5.0 7.5 10.0 12.5 15.0 17.5 20.0 22.5 25.0 27.5 30.0 40 kg. Cement SO kg. Cement A .45Q .675 .900 1.125 1.350 1.575 1.800 2.030 2.250 2.475 2700 B .375 .563 .750 .938 1.125 1.313 1.500 1.688 1.875 2.063 2.250 C .300 450 .600 .750 .900 1.050 i 200 1.350 1.500 1.6S0 1.800 .350 .525 .700 .87S I.oso 1.225 1.400 1.575 1.750 1.925 2.100 B .300 .450 .600 .750 .900 1.050 1.200 I .350 1.650 C .250 .375 .soo .625 .750 .875 1.00 1.125 1.250 1.375 1.500 Sand cu m. .0250 .0375 .osoo .0630 .0750 .0880 .1000 .112S .1250 .1380 .1500 Gravel ce. m. .050 .075 .100 .125 .150 .17S • .200 .225 .250 .275 .300.

Scene 12 (5m 24s)

SOLUTION: 1. Solve for the pavement area Area = Width x Length A = 3.00 x 5.00 A = 15 squared meters 2. Refer to Table 1-3. Along 10 cm. slab thickness under 40 kg. cement class “C” mixture, multiply; Cement: 15 x .600 = 9.0 bags Sand: 15 x .050 = .75 cu. m. Gravel: 15 x .100 = 1.50 cu. m. 3. Compare this quantity to that Illustration 1-1, the results are the same.

Scene 13 (6m 5s)

ELEVATION CROSS SECTION X-X 1-12 COCUMN. 1-7 SQUARE CONCRETE COLUMN Estimating the quantity of materials for concrete post or column can be done in two simple ways: By Volume Method and By Linear Meter Method.

Scene 14 (6m 18s)

TAE 1.1 FROM TO METER Acuü 2 8 9 10 11 12 13 14 15 16 18 20 .050B .0762 .1016 1270 .1524 .1778 .2032 .2286 .2540 .2794 304B .3302 .3556 3810 .4064 .431B 4572 4826 .5080 02S 050 075 .100 .125 .150 .175 .200 225 .250 .27S .300 .325 .350 .375 400 .425 475 24 30 37 40 .5588 .5842 .6096 .6804 .6858 .7112 .7366 .7620 .7874 .8128 8382 8636 .8890 .91" .939e 9652 1.016 .525 .575 .625 .675 .700 .750 77S .82s 875 .975 1.00.

Scene 15 (7m 15s)

1-8 ESTIMATE SQUARE CONCRETE COLUMN BY LINEAR METER METHOD.

Scene 16 (7m 49s)

A concrete column is 7.00 meters high with a cross sectional dimension of 20 by 20 inches. Determine the quantity of cement, sand, and gravel content of the column if there are 8 columns in a row using class "A" concrete. CROSS.

Scene 17 (8m 29s)

1-9 POST AND FOOTING. Estimating the quantity of materials for concrete post and footing could be done by: Volume Method Area and Linear Meter Method combined for post and footing.

Scene 18 (8m 43s)

SOLUTION: By Volume Method Find the volume of 12 posts Volume = Sectional Area x Height x No. of Posts V = (.40 x .40) x 4.00 m x 12 posts V = 7.68 cubic meters 2. Solve for the volume of 12 footing slab V = (1.20 x 1.20) x .20 m x 12 posts V = 3.456 cubic meters.

Scene 19 (9m 17s)

SOLUTION: By Area and Linear Meter Method 1. Find the length of 12 posts L =12 posts x 4.00 m. height L = 48 meters 2. Refers to Table 1-4. Along the 40 x 40 cm column size class “A” mixture, multiply; Cement:48 x 1.440 = 69.12 bags Sand: 48 x .080 = 3.84 cu. m. Gravel: 48 x .160 = 17.68 cu. m. 3. Find the area of the footing slab Area =12 posts (1.2 x 1.2) L = 17.28 square meters.

Scene 20 (10m 12s)

SOLUTION: By Area and Linear Meter Method 1. Find the length of 12 posts L =12 posts x 4.00 m. height L = 48 meters 2. Refers to Table 1-4. Along the 40 x 40 cm column size class “A” mixture, multiply; Cement:48 x 1.440 = 69.12 bags Sand: 48 x .080 = 3.84 cu. m. Gravel: 48 x .160 = 17.68 cu. m..

Scene 21 (11m 6s)

1-10 RECTANGULAR COLUMN. The procedure in estimating rectangular column is practically the same as that of the square column.

Scene 22 (11m 29s)

SOLUTION: By Area Method 1. Find the length of the 8 columns L =8 columns x 5.00 m. height L = 40 meters 2. Refers to Table 1-4. Along with 40 x 60 cm column size under the 40 kg. cement class “A” mixture, multiply; Cement: 40 x 2.16 = 86.4 bags Sand: 40 x .120 = 4.8 cu. m. Gravel: 40 x .240 = 9.6 cu. m..

Scene 23 (12m 18s)

1-11 RECTANGULAR BEAM AND GIRDER. Beam – strong horizontal piece of reinforced concrete for spanning and supporting weights. Girder – a beam that is carrying or supporting another beam..

Scene 24 (12m 30s)

SOLUTION: By Volume Method 1. Find the volume of the beam V = (.25 x .40) x 8 m. span x 5 pcs. V = 4 cubic meters 2. Solve for the volume of the girder V = (.40 x .60) x 16 m. span x 2 pcs. V = 7.68 cubic meters 3. Total volume of the beam and girder Total Volume = 4 + 7.68 V = 11. 68 cubic meters.

Scene 25 (13m 2s)

1-12 CIRCULAR COLUMN. Estimating the materials for circular column is a typically the same as the volume method with the aid of Table-2. However, Table 1-5 was also prepared for circular problems.

Scene 26 (13m 41s)

A circular concrete column has a diameter of 60 cm by 6.00 meters high. Find the concrete materials required if there are 5 columns in the same size in a row..

Scene 27 (13m 53s)

SOLUTION: By Volume Method 1. Solve for the cross sectional area of the beam A = ??^2 or A= 0.7845?^2 A = (O.7854 x .〖60〗^2) =.283 sq. m. 2. Find the volume of one column V =.283 x 6 m. ht. = 1.698 cu. m. 3. Solve for the volume of 5 columns Total Volume: (1.698 x 5) = 8.49 cu. m. 4. Refer to Table 1-2. Using 40 kg. cement class “A” concrete, multiply; Cement: 8.49 x 9.0 = 76.4 bags Sand: 8.49 x .50 = 4.24 cu. m. Gravel: 8.49 x 1.0= 8.49 cu. m..

Scene 28 (14m 55s)

1-12 CIRCULAR PIPE. Circular Pipe is much in demand for small and medium drainage construction. The use of drainage structure materially save cost, time, and labor cost as well..

Scene 29 (15m 30s)

A road construction requires 12 pieces of 90 cm. diameter concrete pipes for drainage purposes. Determine the quantity of cement, sand, and gravel needed to manufacture the said pipes using class “A” concrete. (Excluding reinforcement which will be discussed in Chapter 3).

Scene 30 (15m 47s)

SOLUTION: By Volume Method 1. Solve for the gross volume of the concrete pipe Formula: V= 0.7845?^2H V = 0.7845 x 〖1.10〗^2 x 1= .950 cu. m. 2. Solve for the volume of the hole V = 0.7845 x ?^2H V = 0.7845 x 〖.90〗^2 x 1. = .636 cu. m. 3. Subtract result of step 2 from step 1 to get the net volume of the concrete pipe. Vc = .950 - .636 = .314 4. Total volume of the 12 pipes Vt = .314 x 12 = 3.768 cu. m..

Scene 31 (16m 33s)

THANK YOU!.