[Audio] Good day everyone, I would like to present to you my report on safety and health status and accomplishment for the month of June 2024..

Scene 2 (9s)

[Audio] We have a total of 25 projects, 5 dike road, 15 water system level 2, 2 flood control, and 3 coastal road. Here is also the lists of project sites I visited and not visited in this month, Start with the project site I visited are, 23SG068A, 23SG068C, 23SG035, 23SG037, 23 0 52, 23 053, 23 0 55, 24SG003, 24SG002, and TC02324. While the site I did not visited are, 23SG070B , due to STOP OPERATION, at 23SG070A is under SERVICE PROVIDER, 23SG068B is only in DRILLING STAGE, 23SG068B is also in STOP OPERATION, 23SG048a and B is also in STOP OPERATION, and at site 23SG067-A and B are under the SERVICE PROVIDER, and TC02325 are not yet started..

Scene 3 (1m 30s)

[Audio] Here is also the completion percentage as of June 5, 2024 in our project sites: for twenty three zero fifty two, 79.12%, 23SG035, 71.61%, 23SG037, 61.75%, 48.91% for twenty three zero fifty three, 84.67% for 23 0 55, 42.82% for 23SG070 cluster, 40.24%, 23SG068 cluster, 13.99% for 23SG067 cluster, 37.31% for 23SG066 cluster, 24.20% for twenty four zero 44, 35.7% for 24SG003, and 39.92% for 24SG002. Please note that the other project sites did not yet submit their weekly accomplishment report, and not yet started due to some incomplete requirements..

Scene 4 (2m 41s)

[Audio] On the consolidated record in accident statistics report for the year 2024, we have the total of 4 accident, incident not included, 1 for February, 2 for march, and 1 for May 2024..

Scene 5 (2m 59s)

[Audio] A safety toolbox was conducted to the different project sites under our team to address pertinent safety-related concerns. These concerns encompassed the utilization of personal protective equipment (PPE), implementation of housekeeping programs, promotion of health awareness, adherence to safe working procedures, accident prevention measures, application of control on identified hazards and risks, as well as compliance with site safety rules and policies. Also, the focal points of the meeting included emphasizing the critical importance of fostering a safe and healthy work environment, preventing unforeseen accidents, implementing a good housekeeping program, and ensuring strict adherence to site safety rules, policies, and guidelines. The meeting aimed to instill a strong culture of safety and well-being while promoting a cohesive and secure work environment for all personnel involved in the project..

Scene 6 (3m 53s)

[Audio] We oversee the installation of the security fence, fire extinguishers, safety posters, reminders of site safety and security policies, and tsunami emergency preparedness to enhance safety awareness at the TC02324 and 24SG002 project site..

Scene 7 (4m 14s)

[Audio] A comprehensive site monitoring and walkthrough inspection were carried out at 23sg035, 23sg037, and 23, 052 during the course of site operations. The primary objective of these activities was to assess the sufficiency of potable water supply, the provision of temporary shelter, and the availability of adequate shaded areas to facilitate work under extreme heat conditions. In addition, particular attention was given to ensuring the presence of spotters and guides during heavy equipment operations..

Scene 8 (4m 49s)

A construction site with a bulldozer and workers Description automatically generated.

Scene 9 (5m 8s)

[Audio] A fire extinguisher inspection also conducted with the results of the following: Fire extinguisher easily accessible and unobstructed, Fire extinguisher mounted securely and at the proper height, Fire extinguisher free of visible damage, such as dents, corrosion, or leaks, Hose and nozzle in good condition and free of cracks or damage, Pressure gauge indicating that the extinguisher is fully charged, Safety pin and tamper seal in place and intact, operating instructions and labels clearly visible and legible, Inspection tag or label up-to-date and properly filled out..

Scene 10 (5m 46s)

[Audio] There are also some other task and accomplishments that has been performed, one of this is supervision of installation of safety posters and signages at site, a site safety orientation to the new safety officer, and serves as a resource speaker to Mandatory 8 hours safety and health training for employees..

Scene 11 (6m 5s)

[Audio] We wish to tackle our Concerns and issues on the following; Mandatory OSH compliances to be included on service provider contract, Clarification on utilizing medical assistance fund thru petty cash fund by Project engineer, and Follow up on status for Medical Clearance to be include in pre-hiring requirements, and Performance evaluation: the Safety habit.. That's all, and Thank you...