[Virtual Presenter] Welcome and thank you for joining us today as we discuss the physical technical inspection of Meridian Power Inc. (M-P-I--). We will be discussing the company structure technical and financial considerations environmental safety and security operations and other matters related to its operations and maintenance. We hope that this presentation provides a comprehensive overview of the power plant and that everyone here today leaves with a better understanding. Let's get started!.
[Audio] On slide 2 we will discuss the various considerations for the meridian power I-N-C--. (M-P-I--) Physical Technical Inspection. This includes legal considerations such as company structure and overview organizational structure and plant overview. We will also cover technical considerations like operations and maintenance agreement single line diagrams process flow diagrams plant equipment specifications and power plant operation procedures. In addition we will address financial considerations such as project cost sources of funds and project financing and five-year financial forecasts. Finally we will review other considerations such as environmental safety security operations and procedures and project community development..
LEGAL CONSIDERATIONS.
COMPANY OVERVIEW ..
[Audio] Today MPI has been operating for two years after its ownership was transferred from C-P-P-C to veco in 2023. M-P-I operates a 70.59 megawatt diesel power plant with 10 units and a rated capacity of 7.59 megawatt per unit. M-P-I provides Ancillary Services to the Visayas Grid and also facilitates wholesale electricity spot management for its excess capacity..
Meridian Power Inc. (MPI) Vivant Energy Corporation 100% COMPANY OVERVIEW Company Structure.
[Audio] Today I'm here to present an overview of the physical technical inspection for Meridian Power Inc. (M-P-I--). Our inspection covers the structural components of the company including Vivant Corporation veco VEC HDFE Infracore Sgpdc Transcore SIAEC 1590 EC vidc Prism V-R-E-C vigc V-R-V-C L-W-E-C COREnergy A-H-C Delta P Hybrid DPI Abovant Hydrocore Inc S-P-H-C V-C-C-I CIPC Buskowitz SGC Watermatic Philippines L-P-E-C B-P-C C-E-D-C M-P-I Wmp Sea T-V-I Isla Norte V-G-P-C N-B-P-C C-R-E-C I-M-C-C S-C-E-C V-M-H-I M-P-C A-E-C Flows L-P-C-I Sprec B-R-P-C Generation RES Distribution Holding Company A-P-I Ppwrlc Solar Retail Infrastructure Real Estate VVT Solar B-E-C Gledc SolEnergy and NMCWC. We also have additional information regarding the ownership of PRISM Bpc & Nbpc and W-M-P S-E-A as well as some portions of G-P-I shares. Our inspection allows us to better understand the composition and structure of this vital business entity. Thank you..
[Audio] Meridian Power Inc. was founded by a group of experienced and talented entrepreneurs from the energy sector bringing decades of experience and a strong striving for success. The aim of M-P-I is to deliver energy solutions which are reliable efficient and environmentally friendly for various markets. Our core team and specialised consultants have the capabilities to design build and manage MPI's power plants in an economical way while also aiming to maintain the highest standard of quality and minimise our carbon footprint..
[Audio] At Meridian Power Inc. we are proud to be home to a 70.590 megawatt Bunker C-Fired Power Plant located in the Old veco Compound in Brgy. Ermita Carbon Cebu City. This power plant is equipped with MaK Motoren GmbH and A-V-K Deutschland GmbH & Co. KG engines and generators respectively. The power plant was test and commissioned on October 10 1998 and began commercial operations on November 15 1998. Our power plant is connected to the Don Gil Garcia Substation through the 69 kilovolts Line owned by veco and is the off-taker of A-S-P-A N-G-C-P and wesm..
[Audio] The organizational structure of M-P-I is headed by the O&M A-V-P Facility Head John Paul Pantino. Maintenance Manager Bernardo Buanghug and Operations Manager Marlon Michael Negrido report to him. They are responsible for carrying out daily operations and maintenance of the facility in an efficient and effective manner..
[Audio] M-P-I is dedicated to maintaining the highest standards of conduct and quality. We recognize the importance of having a strong organizational structure and we are proud to have a skilled team of personnel to provide management supervisory technical and non-technical administrative support. Together this team helps to ensure that M-P-I runs smoothly and efficiently..
TECHNICAL CONSIDERATIONS.
[Audio] For the Project Construction phase of Meridian Power Inc. (M-P-I--) to progress to Commercial Operation a comprehensive technical inspection of the facility must be conducted to assess its compliance with engineering standards and safety requirements. It is imperative that M-P-I has all required documentation and certification documents in place prior to facility operation. Such measures are necessary to ensure the facility runs optimally with no adverse environmental impact..
PROJECT CONSTRUCTION TO COMMERCIAL OPERATION.
[Audio] The slide illustrates a single line diagram of Meridian Power Incorporated's facility up to their connection point. This diagram offers an overview of all the components essential for the smooth functioning of their operations. By having this diagram on hand they can quickly detect any likely issues within their facility..
SINGLE LINE DIAGRAM Up to Connection Point Facility MERIDIAN POWER INC..
SINGLE LINE DIAGRAM Up to Connection Point Facility MERIDIAN POWER INC..
SINGLE LINE DIAGRAM Up to Connection Point Facility MERIDIAN POWER INC..
SINGLE LINE DIAGRAM Up to Connection Point Facility MERIDIAN POWER INC..
[Audio] The following is a single line diagram of the facility currently being reviewed by meridian power I-N-C--. (M-P-I--). The diagram reflects the connection point of the facility providing meridian power I-N-C--. (M-P-I--) with a reference to assess both the physical and technical structures of the facility..
[Audio] We'll be taking a look at the protective schemes and system integrities that will be addressed during the physical technical inspection from May 14-16 2024. Our procedures will guarantee the highest levels of safety and security for all involved. We will handle any additional requirements during the inspection if necessary..
[Audio] Power generation is conducted by two 50 M-V-A diesel generating sets. The diesel is delivered to our H-F-O main storage tanks and the H-F-O buffer tanks and separated. The H-F-O Booster Module is used for H-F-O delivery while the H-F-O service tanks provide H-F-O Diesel delivery. Finally the Electrical Grid is connected and customers are changed according to the AORVTE UR PTO..
[Audio] MaK Motoren GmbH Germany's Plant Equipment Specifications are covered by this technical slide. Featuring a 16 CM 32 V-engine with a rated speed of 720 rev/min a bore/stroke of 320 millimeters/420 millimeters an engine power of 7680 kW and a weight of 84 480 kilograms its mean piston speed is 10.1 m/s and mean effective pressure is 23.7 bars..
Specifications Details Firing Order A1-B3-A3-B5-A5-B7-A7-B8-A8-B6-A6- B4-A4-B2-A2-B1 Bank A / B = left / right viewed from drive end Turbo Charger Type ABB TPL 65-A30 Governor Woodward UG40 Actuator Fuel Industrial Diesel Oil – start up & shut down operation Heavy Fuel Oil – normal operation 180–230 cSt @ 50ºC SFOC* @100% 178 g/kWh Lube Oil SAE 40 / Shell Argina XL40 SLOC 0.6 g/kWh, ± 0.3 g/kWh PLANT EQUIPMENT SPECIFICATION Nameplate Ratings - Engine.
[Audio] At Meridian Power Inc. (M-P-I--) we are currently analyzing the plant equipment in order to ascertain its technical characteristics. This is the A-V-K Deutschland GmbH & Co KG a self-regulated brushless generator from Germany. It operates at a voltage of 13800 volts and a frequency of 60 Hz featuring 10 poles and a speed of 720 R-P-M--. Its generator power is 7373 kWe and 9216 kVA accompanied by a current of 394 ampere and a weight of 30 500 kilograms. The cooling medium is air at 40°C with an airflow rate of 8.6 m3/sec contained within an I-P-2-3 enclosure with Class F insulation..
[Audio] The Plant Equipment physical and technical aspects inspection reveals a blackstart unit engine that is a Caterpillar D-3-5-3-D with voltage-frequency of 240-480V/60hz 6-pole 1200rpm speed and generator power of 250kWe/312 kilovolts ampere. It features a 6-cylinder 4-stroke diesel engine with 405 HP power and liquid-cooled radiator as the cooling medium..
[Audio] meridian power I-N-C--. will conduct a physical technical inspection from May 14th to 16th of 2024 which will cover the Blackstart Unit Generator Specifications. The details of the Generator are Manufacturer: Stamford / K-H-T Deutz Model: WML 120/2 Voltage/ Frequency: 480 V/ 60 hz 4 Poles/ Speed: 1800 rpm 104.8 kWe 131 kVA Weight: 458 and Cooling Medium: Liquid Cooled with Radiator Cooling Medium I-P-2-2 with an Enclosure/ Insulation..
[Audio] MPI's upcoming physical technical inspection will include a review of our S-C-A-D-A System. S-C-A-D-A stands for Supervisory Control and Data Acquisition a computer system designed to collect record and analyze data from plant equipment. The inspection will evaluate the system to guarantee that it meets our criteria and is up to date with the most recent technological advancements..
[Audio] M-P-I Metering Facility is equipped with a range of sophisticated measuring and diagnostic equipment such as real-time flow meters pressure and temperature sensors and highly advanced diagnostic tools. These tools provide M-P-I with the ability to accurately and reliably measure oil gas and other natural resources as well as the capability to identify potential problems ahead of time. This allows for the smooth running of MPI's upstream production and storage operations..
[Audio] At Mpi we specialize in performing physical technical inspections of veco Metering Panels. Our team of experienced professionals is knowledgeable in delivering efficient and reliable information. We recognize the significance of meticulously examining and documenting the state of the equipment and its components to guarantee precise documentation of the inspection. We strive to provide the utmost attention to ensure the accuracy of our results..
[Audio] We will conduct a review of the start-up and shutdown procedures provided by O&M at the M-P-I Physical Technical Inspection. Our team of experienced engineers will analyze these procedures to ascertain that all safety regulations and protocols are adhered to. Additionally we will conduct an independent evaluation of the procedures and offer recommendations to maximize plant efficiency..
POWER PLANT OPERAION PROCEDURE Start-Up and Shutdown Procedures (Provided by O&M).
[Audio] meridian power I-N-C--. (M-P-I--) recognizes the significance of maintenance and preventive steps to guarantee a smooth operation. Our Physical Technical Inspection from May 14-16 2024 will offer a full assessment of existing protocols for power plant operation and preventive maintenance. Our experienced professionals will craft a customized action plan and program and help with its execution. Through this proactive method meridian power I-N-C--. (M-P-I--) can ensure the dependable and secure operation of your power plant..
FINANCIAL CONSIDERATIONS.
[Audio] For Slide 35 of the meridian power I-N-C (M-P-I--) PHYSICAL technical INSPECTION from May 14-16 2024 we will discuss the project cost and sources of funds. This is a critical aspect of any project review as it will inform the potential success or failure of the project. Our team will explore the estimated cost of the project and provide an analysis of various sources of funds their availability and potential implications to budget and timeline..
[Audio] Our five-year financial forecast for M-P-I is highlighted in the next slide. This slide shows estimated operating expenses and revenues for the upcoming five years. Closely examining our financial situation is essential as it helps to guarantee successful project outcomes. Through prudent monetary management we can ensure that all projects will be successful..
OTHERS.
[Audio] MPI's Environmental and Safety Operations and Procedures are reviewed regularly to ensure compliance with applicable regulations. Amendments are made to ensure the highest standards of safety and environmental protection are met. An Environmental Compliance Certificate is issued twice a year and any amendments are addressed between those periods..
[Audio] Meridian Power Inc. takes pride in safely managing its operations and procedures. Our Discharge Permit is an important assurance that our company complies with relevant environmental standards as well as local regional and international regulations. This permit safeguards against any potential adverse impact of our activities on the environment or public safety..
[Audio] Our company's operations will be inspected for physical and technical compliance with the Environmental and Safety Operations and Procedures Permit to Operate issued by the local government in order to ensure that all of our facilities and operations comply with local laws and regulations. We are committed to upholding the requirements of this permit and to protecting the environment and our people. Our comprehensive measures and operations to meet these requirements give us confidence that the inspection will be successful..
[Audio] M-P-I will review and assess current Environmental and Safety operations procedures as well as discharge permit and permit to operate. This review is to identify areas that require improvement or amendment in order to be in compliance with regulations and the company's safety standards. Our team is well-equipped with the expertise and knowledge necessary for ensuring effective operations..
[Audio] M-P-I is dedicated to providing outstanding environmental and safety operations and procedures. We would like to present you an overview of our water permit. This permit requires us to supply data assessment of the water quality and quantity to local governments. Moreover it is obligatory for us to carry out regular testing of the water and make adjustments to the water levels and take proactive precautions for environmental preservation. We are devoted to upholding the greatest standards in environmental security and water purity and observing all applicable regulations..
ENVIRONMENTAL & SAFETY OPERATIONS AND PROCEDURES Water Permit.
[Audio] Meridian Power Inc. is committed to environmental and safety operations and procedures. This entails adhering to the Environmental Compliance Certificate (E-C-C--) conditions by regularly submitting the State of Environment (S-M-R--) and Compliance Monitoring Report (C-M-R--) segregating solid waste generated into recyclable and residual waste which are collected by accredited collectors and disposing biodegradable waste into a compost pit. Collectively these comprise our Total Waste Recycling System..
[Audio] M-P-I prioritizes safety and security of operations personnel and visitors. On-site orientation and the issuance of personal protective equipment is offered. Registry log book must be logged on by all personnel and visitors and the plant site is under the surveillance of C-C-T-V-. Compliance to external safety and environment inspections are ensured and drills for fire oil spill and evacuation are conducted. Additionally best safety operating practices are followed and dole O-S-H reports are regularly submitted..
[Audio] M-P-I takes security and safety very seriously. Our Security Guards have extensive training and are on a 12 hour shift rotation. Access control points are in place to ensure that the perimeter is secure. Our Security Operations Center runs 24/7 and is tasked with monitoring a large number of C-C-T-V cameras. The radio communication system gives us the opportunity to link to law enforcement and disaster response agencies. Additionally we regularly hold trainings drills and simulations exercises as preparation for any potential risks or threats..
[Audio] Vivant Foundation Inc. has been actively involved in Corporate Social Responsibility projects in the past. These include supporting the K-12 system promoting innovation through S-T-E-M education building a science laboratory donating science equipment and converting a classroom to a computer laboratory. This year the foundation has further committed to MPI's various community development projects through its 2021 Brigada Eskwela initiative..
[Audio] M-P-I has allocated funds to a dedicated trust account that is deposited with the Philippine National Bank with the three separate account names having the account numbers 300270006260 300270006271 and 300270006237 respectively. These accounts currently have a balance of 604 281.15 pesos 604 281.15 pesos and 1 365 927.82 pesos at the 3002-BANILAD-ForTUNA Depository and Issuing Branch..
[Audio] We have reached the end of this presentation and I would like to thank you for your attention and reflect on the information we have presented. meridian power I-N-C--. is dedicated to providing the highest-quality physical technical inspection and is eager to collaborate with Vivant Corporation for the duration of the inspection. We highly prioritize collaboration and are certain that our knowledge and perspectives will add to the project. Once again thank you for your time and attention. Have a great day..