[Audio] Health and Safety Induction The purpose of this induction is to detail Kealy site safety rules and procedures as well highlight any hazards which are applicable across Kealy project sites. Once you have completed this induction you will still need to attend a site-specific briefing the first day you attend site, carried out by the Site Management Team..

Scene 2 (30s)

[Audio] When entering and exiting our sites all persons are asked to do so with extreme caution as this route can be busy. All persons are asked to be courteous and give way to pedestrians and vehicles. Project speed limit is 10 kilometers per hour and must be obeyed at all times. No vehicles are permitted to enter the construction zone all vehicles must be reversed parked in the compound carpark All vehicle entering this site will be subjected to random searches by security with photographs taken for the security of your tools and equipment..

Scene 3 (1m 4s)

[Audio] Site Inductions: All operatives must have all documentation submitted prior to accessing site, failure to do so may result in personnel being refused entry. Safe Pass: All employees on-site must be in possession of a valid Safe Pass or C-S-R card to be forwarded to safety Manager. NO safe pass NO START CSCS: Relevant C-S-C-S training must have been completed where required to be forwarded to safety officer (for example excavators, telehandler, lugs et cetera) Mobile Phones: Mobile phones use is only permitted in safe areas away from site traffic. Smoking: STRICTLY NO SMOKING INDOORS any person found smoking shall be immediately dismissed and barred from entering any Kealy site. Manual Handling: All employees on-site must be in possession of a valid MH cert to be forwarded to the Site team NO Manual Handling NO START.

Scene 4 (2m 1s)

[Audio] Alcohol and Drugs: The consumption of alcohol or illegal drugs on Kealy sites is strictly prohibited. Persons which site management believe to be under the influence or suffering from the aftereffects of alcohol or illegal drugs will asked to leave the construction zone immediately and may be required to undergo an alcohol / drugs test. Kealy Reserves the right to test any persons on their sites to undergo both specific or random alcohol / drugs test during works or following an accident. Site Hours: Site hours are 07:00hrs – 19:00hrs (Mon-Fri) 09:00hrs – 13:00hrs (Sat) Planning permission start / finish times must be adhered to. No work outside these hours without prior arrangements with Kealy site management. Machinery & Equipment: All machinery being brought on-site (including lifting equipment and lifting tackle) must carry certificates of thorough inspection G-A-1--. Machinery will Not be permitted to enter the site under any circumstances without the appropriate documentation..

Scene 5 (3m 13s)

[Audio] Safety Behaviour: If you deem any task to be unsafe You must S-T-O-P immediately and report it to the site manager / foreman. It is the responsibility of all operatives to understand and comply with their individual contractors Method Statements and Safe Working Practices. Employee Health: Any health conditions which could affect your safety or that of others must be reported to Kealy management immediately on a confidential basis. Interface with the Public: All employees are expected to always behave in a respectful fashion towards members of the public and ensure that all necessary safety precautions are taken to ensure public safety. Kealy Construction does not and will not tolerate any kind of abuse towards personnel on our site, repercussions for such occurrences will result in being removed from site. Please note: Site rules and/or conditions may change as the project developments. Kealy will ensure that all employees & sub-contractors are updated as necessary in a timely fashion..

Scene 6 (4m 19s)

[Audio] Lifting Equipment Inspections: Weekly inspections must be completed on all lifting equipment. G-A-2 must be completed by the operator (teleported, excavator, dumper et cetera) Work at Height Equipment: G-A-3 must be completed for equipment used for work at height (scaffolding, safety harness, steps, hop-ups et cetera) Portable Electrical Equipment: All portable electrical equipment must operate on 110v and be subject weekly inspection. Records of inspections must be returned weekly to the site office, every Monday by 12:00hrs or companies will be stood down. Safety Briefings: Pre-start safety briefings will be carried out on a daily basis by the site manager / foreman. Coordination with subcontractors will be discussed. Site Visitors: Visitors to site will Not be permitted onto site without having submitted the visitors Covid-19 self-declaration form and completing the Visitor Safety Briefing with safety personal. There will be no exceptions..

Scene 7 (5m 27s)

[Audio] Mandatory 3 Point P P E System Hard Hat (No bump caps) These must be worn at all times on site without exception Safety Boots At all times with ankle protection* Hi-Vis At all times.

Scene 8 (5m 49s)

[Audio] Task Based (when your method statement, risk assessments states these are required) Hearing Protection Ear plugs must be worn when noise in your work area is at 80db (if you have to raise your voice to hold a conversion, with earmuffs being worn when noise is above 85db Safety Glasses At all times Respirator or FFP3/2 dust mask Filter mask required for any large amount of dust Face coverings must Not to be used in place of dust masks as they do not offer any protection from dust particles.

Scene 9 (6m 25s)

[Audio] TOILETS! and Welfare facilities are located. The welfare facilities are provided to make your workday more comfortable, and these must be treated with the highest amount of respect. Your fellow workers must also use these, and we contract cleaners to clean daily please don't leave their job any harder than it needs to be. Any person found to be miss treating the canteen or toilets shall be removed from site immediately and be barred from entering any Kealy site in the future. FLUSH! FLUSH! FLUSH! If you pee FLUSH! If you poo FLUSH! If you blow your nose FLUSH! Please FLUSH! The toilet after each use, we are not animals so please don't act like it, FLUSH! FLUSH! First Aid box is located in the site office. Any use of the first aid box must be recorded in the usage sheet enclosed in the box..

Scene 10 (7m 21s)

[Audio] Site logistics Emergency Assembly Point Area Handed Over Office & Canteen Storage Container Toilets Site Boundary.

Scene 11 (7m 35s)

[Audio] Kealy First Aiders. Kealy First Aiders. Site Team Member Site Team Member Health & Safety Manager Paul Kirwan.

Scene 12 (7m 44s)

[Audio] Report all Accidents Incidents Near misses Use of the first aid box The reporting of these shall be strictly treated in a non-blame manor so please report all the above as it helps us insure your near miss is not someone else's serious Accident.

Scene 13 (8m 1s)

[Audio] Anybody caught tampering with fire point or emergency equipment will be IMMEDIATELY dismissed from site.

Scene 14 (8m 17s)

[Audio] Emergency Procedures 1. In the event of a fire, the fire alarm will be activated – the air horn sounded. 2. Kealy Fire Wardens/Foremen will implement the Fire and Emergency procedure and direct all personnel to the site assembly point. In the carpark 3. Do not stop to collect tools or personal belongings. 4. Roll call will be taken to confirm all personnel are present. 5. Do not leave the site under any circumstances until the emergency has passed and you are informed of such by a member of Kealy Site Management..

Scene 15 (8m 56s)

[Audio] Plant & Machinery Machinery & Equipment: A-L-L machinery being brought on-site (including lifting equipment and lifting tackle) must carry certificates of thorough inspection GA1. Machinery will Not be permitted to enter the site under any circumstances without the appropriate documentation. A-L-L machinery and lifting equipment must be inspected daily and included in the weekly G-A-2 inspection form. A-N-Y defects found must be included in the form with a new inspection completed with the repair engineers report attached to the inspection form in which the fault was highlighted.

Scene 16 (9m 31s)

[Audio] Plant & Machinery Workers never walk close to a working machine unless the driver is aware of your presence and has stopped operations ALWAYS leave a minimum gap of 1 meter between your and the piece of plant equipment. never attempt to squeeze between the plant machine and a scaffold, building, or other obstruction Pedestrian walkways have been set up around site with these being segregated from vehicle routes and designed crossing points all operatives must use these walkways.

Scene 17 (10m 1s)

[Audio] Working at Height Working at height and falls from height is the biggest cause of fatality in the construction industry A-L-L access platforms including mobile access towers, and trestles must be erected by a competent person in line with the manufacture's instructions. A-L-L platforms and leading edges must be fitted with proper edge protection Work at Height Equipment: G-A-3 must be completed for equipment used for work at height (scaffolding, safety harness, steps, hop-ups et cetera) Records of inspections must be returned weekly to the site office. ALWAYS Protect holes, leading edges and fragile materials ALWAYS Consider weather conditions IF IN doubt speak to your supervisor.

Scene 18 (10m 45s)

[Audio] Scaffolding If the scaffold is struck by plant or machinery if must be reported immediately to Kealy Site manager Report A-N-Y scaffolding safety concerns as soon as possible to Site Manager If in doubt – STOP, ASK ! DO Not work on scaffold which is not complete or safe It is against the law to adjust amend build or dis-mantle scaffold without a C-S-C-S ticket Any person found tampering with scaffold shall be removed from site Do not use scaffolding planks for any other purpose than they are intended Always check area is safe before commencing work, an in date safe tag must be beside the ladder access Never overload the scaffold loading bay max weight shall be marked on each loading bay You have a legal duty to ensure your safety and that of others who may be affected by your acts or omissions..

Scene 19 (11m 36s)

[Audio] 20 Second Scan Before you start any task "Take Time" to do a "20 second scan" Is it safe? Are all required safety precautions in place? Do you have safe access Have you read and understood the Safe Method of Work Will anyone else be affected by your work ALWAYS leave an area in a safe condition Barrier off work areas Clean as you go is being adhered to.

Scene 20 (11m 59s)

[Audio] Observe & Report Report A-N-Y safety concerns as soon as possible to Site Manager If in doubt – STOP, ASK ! If you see something that could endanger you or someone else on-site – take ACTION & report (I-T ) Do not leave hazards for others Always check area is safe before commencing work You have a legal duty to ensure your safety and that of others who may be affected by your acts or omissions..

Scene 21 (12m 26s)

[Audio] Disciplinary Procedure Minor safety breach: Conversation had with operative about wrong doings Repeated Minor safety breach: operative supervisor asked to discuss with the operative and issue toolbox talk. Brought to employer's attention requesting a report on preventive measures Persistent or safety breach which may result in serious injury: Removal from site with reinduction before restart. Brought to employer's attention requesting a report on preventive measures Safety breach which may result in serious injury or death: Permanent removal from site. Brought to employer's attention requesting a report on preventive measures.

Scene 22 (13m 10s)

[Audio] Safe Plan of Action S-P-A S-P-A to be completed at least once per week when works exceed company rams – No Exceptions. Crew must sign on daily to relevant S-P-A for works. Copies to be retained on Kealy secure server. S-P-A compliance will be audited by the E-H-S Dept. & Site Mgmt..

Scene 23 (13m 33s)

[Audio] M-A-I-N site HAZARDS three highlighted in red Excavations Machinery Operations Buried Services Work at height Use of tools and equipment Use of concrete or cement.

Scene 24 (13m 47s)

[Audio] Permits To Work A Permit to Work (P-T-W--) system is in operation on Kealy construction sites for specific tasks which include the following: Confined Spaces Hot Work Work in proximity to Overhead Lines Excavations / Breaking Ground Ladder Late Works Failure To Comply Will Result In Your Company Being Stood Down.

Scene 25 (14m 9s)

[Audio] Buried Services Before any excavation work is carried out, the presence of any buried services must be identified. Permit to Break Ground in operation. C-S-C-S lugs trained operator to carry out survey. Buried serviced to be marked out on-site and appropriate safety signage erected. Kealy procedure for buried services must be followed..

Scene 26 (14m 31s)

[Audio] Environmental Clean As You Go Waste segregation must be complied with alongside clean as you go.

Scene 27 (14m 50s)

[Audio] Any Questions? Ask the site team when onsite..