[Audio] The extent of compliance for the recommendations from the previous visit for the Bachelor of Science in Civil Engineering Program in Area 8: The Physical Plant and Facilities..
[Audio] Recommendation No. 1: Evaluation of student center utilization is recommended..
[Audio] The student center is located just in front of the College of Engineering building and.
[Audio] it has been utilized to cater the conduct of meetings and various activities of different organizations of the College, even before the onslaught of the COVID- 19 pandemic..
[Audio] The first recommendation is 100% complied..
[Audio] Recommendation No. 2: If budget warrants, ramps leading to the 2nd and 3rd floor of the engineering building may be constructed to facilitate mobility of PWD's..
[Audio] Construction of the ramp has already been considered in the annual procurement plan since the 2019 with the various repairs amounting to Php 300,000.00.
[Audio] The second recommendation is 100% complied..
[Audio] Recommendation No. 3: Suitable toilet facilities accessible to PWD's without requiring assistance maybe designed and constructed..
[Audio] The buildings in the university have toilets for PWD's already especially those that are newly constructed,.
[Audio] like the SSU Convention Center and RIC Building..
[Audio] The third recommendation is 100% complied..
[Audio] Recommendation No. 4: Installing and utilizing appropriate flooring and cleaning materials to prevent the risks of slips among employees and students may be considered..
[Audio] Provision of cleaning materials had already been made and floorings had already been repaired to avoid slips and accidents while walking..
[Audio] The fourth recommendation is 100% complied..
[Audio] Recommendation No. 5: If budget warrants, the canteen may be expanded to accommodate the growing population of the university..
[Audio] The construction of the new food court, which is larger than the existing canteen, is already indicated in the Future Development Plan of the university..
[Audio] The fifth recommendation is 100% complied..
[Audio] Recommendation No. 6: Signages indicating emergency exits in cases of fire and earthquakes may be posted in a conspicuous place of the building..
[Audio] Signages are posted on the emergency exits and.
[Audio] there are also evacuation plans on strategic places of the building..
[Audio] The sixth recommendation is 100% complied..
[Audio] Recommendation No. 7: The exhaust fan may be repaired and proper ventilation is needed in order not to add humidity in the area..
[Audio] Exhaust fan in the canteen had already been repaired by the electrical maintenance and.
[Audio] there is an additional ventilation installed in the area..
[Audio] The seventh recommendation is 100% complied..
[Audio] Recommendation No. 8: Classrooms occupied by teachers may be made spacious and clean, therefore excess cabinets and dividers may be placed in another room/ place..
[Audio] Cabinets and dividers in the faculty room were already used to have an organized arrangement and the cleanliness of classrooms are maintained..
[Audio] The eighth recommendation is 100% complied..
[Audio] Recommendation No. 9: There is a need to further continue repairing the classrooms to provide two exit doors that open outward..
[Audio] The classrooms in the Engineering Building have two exit doors already with outward openings..
[Audio] The ninth recommendation is 100% complied..
[Audio] Recommendation No. 10: Unified storage for athletic equipment may be put in place..
[Audio] There is an existing athletic equipment storage and the plan of the construction for the unified storage of athletic equipment will be considered in LUDIP in the university..
[Audio] The tenth recommendation is 100% complied..
[Audio] Recommendation No. 11: Provision of covered walks may be considered especially from the guard house to the other buildings..
[Audio] The covered walks from the guard house is already constructed..
[Audio] The eleventh recommendation is 100% complied..
[Audio] Recommendation No. 12: Stockrooms may be regularly checked to remove the materials that are considered waste like plastics, among others..
[Audio] Waste materials inside the store rooms had already been disposed and those that could still be recycled were properly arranged..
[Audio] The twelfth recommendation is 100% complied..
[Audio] Recommendation No. 13: The fire extinguishers may contain information cards that reflect the regular monitoring of the same..
[Audio] The fire extinguishers in the rooms/ offices have already been attached with respective monitoring card for fire safety compliance..
[Audio] The thirteenth recommendation is 100% complied..