EMERGENCY EVACUATION PLAN FOR Al ZOUR REFINERY SAFETY CAMPAIGN.

Page 2 (8s)

Title - Emergency Evacuation Plan - Al Zour Refinery- KIPIC-ZOR-HSE-SAF-1209.

Page 3 (34s)

This plan is to document how to notify occupants of a facility about emergency, establish evacuation procedures and routes, provide support for employees to evacuate safely..

Page 4 (1m 12s)

1. Evacuation The organized, phased, and supervised withdrawal, dispersal, or removal of people from dangerous or potentially dangerous areas, and their reception and care in safe areas on immediate basis without delay..

Page 5 (1m 37s)

2. Evacuation Routes All roads which lead to Assembly Points (Local/Main) in a safe manner are called as Evacuation Routes..

Page 6 (1m 58s)

4. GATHERING POINTS Are pre-identified safe location where the evacuees can stay for longer duration before returning to work or being asked to proceed to home or being transported to Civil Defence Shelters. Gathering point shall be used when further evacuation required from units or buildings Assembly Points. There are designated gathering points covering all the Al Zour refinery units and buildings area..

Page 7 (2m 18s)

LIST OF KEY PERSONNEL FOR MANAGING THE EMERGENCY EVACUATION:.

Page 8 (2m 30s)

CHAIN OF COMMAND DURING EMERGENCY EVACUATION:. B.4 Chain of Command for Evacuation in Buildings Area If Further Evacuation Required from Local building Assembly point to Main Gatherjnq point — GL Will Coordinate with Zone ZONE LEADER TRANSPORT COORDINATOR EVACUATION TRAFFIC CONTROLLER (Security Team) INCIDENT/ EMERGENCY Upon Activation of Fire or Gas Alarm immediately evacuate to pre-assigned assembly point under guidance of the Group Leaders GROUP LEADER/ DEPUTY GROUP LEADER EDC OPERATOR HSE COORDINATOR Activates Initial Callout and informs all concerned Team as per ERP Fire Team & Rescue Team Medical Tea m.

Page 9 (2m 53s)

INITIATION/ANNOUNCMENT OF EVACUATION:. Fire and emergency alarms are intended to alert refinery site personnel's that a fire, gas release or other life-threatening situation exists. Upon hearing fire alarm occupants of building Shall: leave the workplace. Immediately evacuate the building via the nearest safe route. reach designated Building assembly point. Obey all directions from group leaders. Authorized Group leader shall be informed and ensure that the floor/passage deputy group leaders about emergency. Authorized Group leader will call immediately to EDC (170), for more information relevant to the incident..

Page 10 (3m 22s)

KEY PERSONNEL ROLES AND RESPONSIBILITIES:. On reaching the assembly point, take head count and fill the “Emergency Head Count Sheet” (Annexure-1) and compare with the daily head count sheet and hand over to the group leader. Group Leaders Group Leader is a designated person within an organization/building who is given specific responsibilities to manage the evacuation of all persons from his/her designated area/Building with co-ordination with deputy group leader during a fire incidents or other emergencies. Focal person for communication with EDC and Ensure that the EDC-170 has been notified. On instructions from EDC, effect evacuation of personnel and Coordinate with deputy group leader and collect all headcount and report to HSE Coordinator for search and rescue. Wait for further instructions from Zone leader/ Evacuation Controller at the assembly points if further evacuation required to gathering point. Deputy Group Leaders If building having numbers of floor/passage / wing, for better control Preferably each floor/passage / wing shall have dedicated deputy Group Leader to manage the evacuation and guide all persons to reach the assembly points by the safest route with assistance of group leader during emergencies. On Hearing Fire alarm/Evacuation Siren or as instructed by group leader Get ready for evacuation. Guide all personnel under his jurisdiction to assembly point and ensure all personnel are evacuated..

Page 11 (4m 20s)

KEY PERSONNEL ROLES AND RESPONSIBILITIES:. Zone Leaders Zone Leader & their alternate are nominated for each zone of Al Zour Refinery. Based on zone leader instruction further evacuation will be carried out from building assembly point to main gathering point of Al Zour refinery buildings area. Zone leader of respective zone shall collect head count details from Group Leaders using Head Count Report form of respective gathering Points/Emergency shelter . In turn, they should inform the head count to the EDC for necessary action. Coordinate with transport coordinator for further transportation of employees from building assembly point to main gathered point of Al Zour refinery buildings area..

Page 12 (4m 58s)

KEY PERSONNEL ROLES AND RESPONSIBILITIES:. Evacuation Coordinator (Shift Safety) Safety Engineers (Shift Safety) approach to the assigned assembly point and guide the group Leaders at assembly point for further action. Evacuation Traffic Controller Shift Security Officer Barricade the incident scene, control the traffic. TRANSPORT COORDINATOR (GENERAL SERVICE): Obtain information regarding evacuation, wind direction, changes in evacuation routes and assembly points from EDC operator and coordinate with respective zone leaders. Obtain the head count from Group Leaders and informed to Shift Fire officer about missing person for rescue. Transport coordinator is a designated person from general service group who is given specific responsibilities to manage the transport in coordination with zone leader. Responsible for the allocation/assigned the buses and bus drivers of to transfer KIPIC / Secondment employees from respective building assembly points to respective gathering point in Refinery. Transport coordinator shall be available for all the shift (covering 3 shift), in case of absence assigned the alternate. Allow only fire services, ambulance and persons holding emergency gate pass. Post security man at outside facility area to regulate the traffic. Barricade the roads where required and guide flow of traffic through appropriate road..

Page 13 (5m 50s)

DISTRIBUTION OF ZONES FOR Al ZOUR REFINERY BUILDING AREAS.

Page 14 (5m 59s)

LOCATION OF GATHERING POINTS AND GATES FOR AL-ZOUR REFINERY TO COVER BUILDING AREA :.

Page 15 (6m 37s)

GATHERING POINT/ MAIN ASSEMBLY POINT FOR CAMPUS AREA:.

Page 16 (6m 46s)

Title - Emergency Evacuation Plan - Al Zour Refinery- KIPIC-ZOR-HSE-SAF-1209.

Page 17 (7m 1s)

EMERGENCY EVACUATION SIRENS AND PUBLIC ADDRESS SYSTEM:.

Page 18 (7m 38s)

EMERGENCY EVACUATION ROUTE MAPs :. EMERGENCY EVACUATION ROUTE MAPS: Refinery safety team shall prepare building Emergency Evacuation route layout and updated periodically in coordination with the asset custodian. Asset custodian shall be responsible for displayed approved drawing at various locations in the building for creating awareness in the employees regarding the evacuation routes etc. Following are some of the important features marked in the drawing: Assembly Points Evacuation routes. First aid box location Fire extinguisher location.

Page 19 (8m 7s)

[image]. DRILL/HEAD COUNT:. DRILLS: Drills are required for assessing the performance of systems and personnel in case of emergency. Periodic evacuation drills are planned and carried out in the Refinery. Various types of drills such as Partial Evacuation Drill, Total Evacuation Drill are planned every year and carried out accordingly. Observations by various Observers are discussed in the post drill meeting and action taken for further improvement..

Page 20 (8m 29s)

DRILL/HEAD COUNT:. HEAD COUNT: Head Count Procedure is being done by group leaders, initially at local assembly point of his respective building and same re-tallied at emergency shelters. In turn, the Group Leader will communicate the Head count of respective assembly point/emergency shelter to the respective Zone leader. Daily attendance data which is taken from KIPIC Portal TACS System should be used to cross check or to ensure no one is missing..

Page 21 (8m 52s)

TRAINING ON EMERGENCY EVACUATION PLAN :. TRAINING: All Key Personnel including Bus Drivers involved in evacuation should undergo training on KIPIC Emergency Evacuation Plan- to know their roles and responsibility during emergency organized by the Safety Team – Al Zour Refinery. Contractor Key Personnel / Safety Engineers / Safety Officer shall attend the KIPIC Emergency Evacuation Plan and train their respective workforce including bus drivers..

Page 22 (9m 13s)

MEANS OF TRANSPORT:. See the source image. All the personnel on hearing the Fire Alarm/evacuation siren should reach the nearest Building Assembly points from where they will be taken to Gathering Point by Buses if further evacuation required. Personnel having pool vehicles should proceed directly to the nearest Assembly Point (Local/Main) and should take with them personnel in route to the capacity of their vehicles..

Page 23 (9m 34s)

GENERAL GUIDELINES DURING EMERGENCY:. Get familiar with Emergency Evacuation routes. Wear Proper PPE for safe evacuation. Know your Local & Main Assembly Points. Know your Group Leader & follow his instruction. Know the Siren for Emergency Evacuation. On hearing the Emergency Siren, reach your respective workplaces and remain alert and wait for further instructions. If you are working on equipment or machinery, stop it and secure it. Do not panic, keep calm. Do not rush, push, or overtake. Do not smoke. Keep noise to a minimum so that instructions can be easily heard. In case evacuation is declared in your area, by considering cross wind direction proceed to declared Local Assembly Point under the guidance of your Group Leader. Use Stairs. Do not use lifts..

Page 24 (10m 9s)

GENERAL GUIDELINES DURING EMERGENCY:. Personnel having vehicles shall proceed directly to the Assembly Point (Local/Main) and try to carry personnel in route to maximum capacity. Do not panic or over speeding while driving. Emergency response vehicle such as ambulance and fire trucks shall be given priority. Vehicles should be parked clear of traffic lanes so emergency equipment has access to the location of the Emergency. On reaching Assembly Point (Local/Main), report to Group Leader for head count. Do not re-enter the building until ‘All Clear’ siren is sounded. Visitors shall follow their escorts. Essential Operating Staff shall remain at their respective station until further instruction from their supervisor. Designated Evacuation Routes and Local Assembly Points may not be the safest on all occasions. In case of suspected hazards, the Group Leader should contact EDC for advice and alternate..

Page 25 (10m 47s)

Thank You. [image] home. [image] home. 3.