[Audio] To BOSS ABG, MADAM RBG, Operation Manager TJS, Project Managers, Co-Project Engineers, Department heads present, and to all, pleasant greetings from PORT OF CLAVERIA team. In the name of our project manager Engineer Ruben B Manrique and my co-project engineer Charlene Joy Antiga, allow me to present to you our week update for the project Rehabilitation/Improvement of Claveria Port Project as of June 16, 2022. Presenting now is Engineer Jeomar A Bautista..

Page 2 (36s)

[Audio] This slide shows the project time elapse as of the date. As reflected, the project has already lapsed 344 calendar days, we are at middle period of the project contract, having an actual accomplishment of 63.941% versus the programmed accomplishment of 64.630% , having a slippage of negative 0.691 percent.

Page 3 (1m 15s)

[Audio] The next slide shows the statement of work accomplishment. This slide reflects the actual project movement per payable item. Those boxed item are the active activities in the previous week..

Page 4 (1m 47s)

[Audio] Again, those boxed item are the items having an accomplishment for the past week. As per table, most active items are under bill number 3 under back up are with roro ramp fill..

Page 5 (2m 21s)

[Audio] To show the summary, same as the one reflected on the time elapsed, we have a negative slippage of 0.690% compared to last week which is positive 0.078 percent.

Page 6 (2m 51s)

[Audio] In particular, bill number 2, item 2.06 : Extraction of existing rocks/ structures prior to the construction of anchor wall, and item 2.07: Removal of existing concrete blocks prior to the installation of anchor wall and sheet piles is an active item last week..

Page 7 (3m 14s)

[Audio] Moreover, under bill number 3, item 3.03: Supply and Install Steel Waling and Splice Plates for Sheet Piles . Item 3.04 : Removal of existing concrete blocks prior to the installation of anchor wall and sheet piles.

Page 8 (3m 36s)

[Audio] Item 3.05: Supply and Install Tie-Rod of Various Sizes at 60 mm x 12 meters Length. Item 3.06: Supply and Place 3,500 psi Concrete for Retaining Walls.

Page 9 (3m 57s)

[Audio] Item 3.07: Supply and Install Steel Reinforcements to Retaining Walls. Item 3.10: Supply and Install Geotextile Fabric.

Page 10 (4m 13s)

[Audio] Item 3.11: Supply and Place Sand and Gravel Fill, and Item 3.15: Supply and Place Aggregate Base Course, are the moving items last week..

Page 11 (4m 29s)

[Audio] On your screen is the documentation during extraction of rock structures prior to laying of anchor wall..

Page 12 (4m 43s)

[Audio] On the left part of the slide is the communication letter from PPA-head office stating the turn-over of the remaining quantity of Concrete blocks. Picture shows the actual retrieval of the blocks for stockpiling...

Page 13 (4m 58s)

[Audio] The diagram reflects the actual status of the installation of steel waling and splice plates. Those areas at yellow box are the areas with the latest accomplishment. Reflected in the diagram that we have a remaining balance for installation of 25 meters or equivalent to 3 sets of steel walling..

Page 14 (5m 20s)

[Audio] The slide shows the documentation of installation of steel walling..

Page 15 (5m 32s)

[Audio] The diagram shows the cutting of piles development. Again, those boxed yellow are the latest accomplishment for the item. In the diagram, all piles has been cut to the required elevation. Thus, under 3.04 is completed..

Page 16 (5m 52s)

[Audio] Actual photo of the cutting of the driven piles up to elevation..

Page 17 (6m 7s)

[Audio] The diagram shows the development update of item 3.05: Supply and installation of tie rod. As per legend, colored blue lines are tie-rods partially installed. Whereas, those colored green are tie-rod considered installed but not installed in actual. Those boxed yellow are the latest accomplishment while those colored red are the previous accomplishment for the item..

Page 18 (6m 36s)

[Audio] Actual photo of installation of tie rod at left side facing sea..

Page 19 (6m 51s)

[Audio] Actual photo taken during installation of tie rod at right side and front side of the reclaimed area..

Page 20 (7m 4s)

[Audio] The diagram shows the actual status of concrete pouring of side structures. Those colored red are the previous accomplishment of pouring. The colored royal blue are areas poured up to second leap of retaining wall as of July 16, 2022. While those in cyan color are areas poured at first leap of retaining wall only. Lastly, those in yellow are area poured at pile cap only. Moreover in the diagram, the colored green and boxed black is the remaining area for pouring of pile cap and first leap of retaining wall in order to close the reclamation area..

Page 21 (7m 46s)

[Audio] This is the recorded pouring accomplishment as of June 25, 2022 to July 16, 2022. For the record, we have poured 261.90 cubic meters in the inclusion date..

Page 22 (8m 2s)

[Audio] In total, we have accomplished 748.49 cubic meter of poured area which is more than fifty percent of the bill of quantity..

Page 23 (8m 24s)

[Audio] Actual photo during concrete pouring of structures at left side facing sea..

Page 24 (8m 36s)

[Audio] Actual photo during concrete pouring of structures at front side..

Page 25 (8m 47s)

[Audio] Actual photo during concrete pouring of retaining wall 1c..

Page 26 (8m 57s)

[Audio] Retaining wall 1c at causeway to connect to pier is already poured to elevation..

Page 27 (9m 5s)

[Audio] the diagram reflects the steel reinforcement installation update. The boxed black is the area prepared with steel reinforcement for pouring at first leap..

Page 28 (9m 27s)

[Audio] Actual photos of steel reinforcement installation..

Page 29 (9m 39s)

[Audio] Actual photos of steel reinforcement installation. In the rightmost side of the slide it is shown that the team is dependent on the lowest tide condition at site which explains why we need to work sometimes early morning or late night..

Page 30 (9m 54s)

[Audio] Actual photo of installation of geotextile fabric..

Page 31 (10m 5s)

[Audio] Item 3.11: Supply and place sand and gravel fill. As per bill of quantity, we have a volume of 35,002 cubic meter versus the actual delivery of 31,205.75 cubic meter. As of today we have a balance of 3,796.25 cubic meter for delivery..

Page 32 (10m 31s)

ITEM 3.11: SUPPLY AND PLACE SAND AND GRAVEL FILL.

Page 33 (10m 41s)

[Audio] Other related site activities conducted but not payable under itesms..

Page 34 (10m 50s)

[Audio] In preparation for the incoming PPA-head office inspection, we designated a team to start correctional plastering to the poured side structures..

Page 35 (11m 0s)

[Audio] Photo of the daily toolbox meeting and the checking of blood pressure prior to deployment..

Page 36 (11m 11s)

[Audio] This slide shows the site overview as of the week..

Page 37 (11m 19s)

[Audio] Project Expenses. Under various materials, the total record on site is 58,765,771.85 pesos. Under Equipment rentals and equipment-related expenses, we have recorded 7,747,377.49 pesos. Lastly for the manpower, 3,420,488.12 pesos. To sum, we have recorded a site expense of 69,933,637.46 pesos, having a remaining budget at QTO of 48,439,388.70 pesos. Please correct us if we have lapses in our recording for future references..

Page 38 (12m 14s)

[Audio] As for the billing status, we have reported at project accomplishment report as of June 25, 2022 an accomplishment of 69.808 percent. More or less billable at 15%..

Page 39 (12m 30s)

[Audio] Equipment status as of July 16, 2022.. Equipment Breakdown: 2-Units Jackhammer 1-Unit Submersible Pump 2- Unit Generator 1-Unit Concrete Vibrator.

Page 40 (12m 47s)

PROJECT CONCERNS. ENGINEERING DIV. / ACCOUNTING. Pending Payables for Various Hardware Materials under RJJ Aristotle Trading – 63k.

Page 41 (13m 0s)

PROJECT CONCERNS. ENGINEERING DIV. / Purchasing Dep’t.

Page 42 (13m 13s)

[Audio] Questions and other discussions.. GIFs For Powerpoint Presentation - 100 Pieces of GIF Animation.

Page 43 (13m 21s)

[Audio] Before I end my slide, allow me to leave a quotation Either you run the day or the day runs you. Make today amazing guys! Good morning once again..

Page 44 (13m 34s)

[Audio] Stay healthy and god bless KKCCDC.. S T A Y H E A L T H Y !.